That it be noted that under a pre-authorised and pre-existing NEC Terms Service Contract for Pier Maintenance the Contractor has prepared, developed and is implementing a plan for the urgent repair works to to stabilise the existing structure and with the goal of enabling the pier to re-open and to avoid further secondary structural damage or loss to business. 2. That the Financial Implications in this Report be noted and the proposed cost of the urgent stabilisation work be authorised to ensure the urgent work can be completed, rather than the Chief Executive rely on the use of the delegated urgency powers within the Scheme of Delegations found at Part 4 of the Councils’ Constitutions. 3. That the total cost of the urgent works be approve and the virements proposed by the Chief Finance Officer and the creation of a contingency fund as set out at paragraph 9.2.3 of the report be authorised. Call In: It was agreed by the Joint Chairs of the Joint Overview and Scrutiny Committee that this item is urgent and cannot be reasonably delayed. Therefore call-in is waived for this item
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
Worthing Pier is a well-loved heritage asset which recently suffered weather-related damage, causing the first significant closure in 25 years on October 9th 2024. A damaged pile had to be removed and an independent structural engineering assessment clearly advised closure was necessary for public safety reasons. The administration has given a clear direction that the works to the pier be prioritised because of the pier’s importance to the town.
Officers have been working hard on a temporary fix, enroute to a more permanent repair, and this report updates members on the work to date, the implications of the short term closure and the proposed next steps. The council's engineering and health and safety teams are working with specialist contractors on a temporary support structure to be installed in the November tidal window with the aim re-opening of the pier in time for Christmas, in support of the key local businesses based there.
Owing to the nature of the damage it is necessary to install a supporting truss in advance of a permanent fix and this solution is outlined in this report. Once this is successfully installed the next step will be to develop the programme of works needed to deliver the permanent fix as well as consider the funding approach needed to support that work. This report sets out for the Committee the steps taken and decisions made in recent weeks to ensure that funds were available to deliver this work.
1. Purpose 1.1. To present an urgent report to Members to provide them with an update on the recent events at Worthing Pier.
1.2To outline the planned temporary fix to the pier and the approach for the next phase of work to deliver a permanent solution.
Recommendations
2.1Members of the Joint Strategic Committee are requested to:-
2.1.1. Note that under a pre-authorised and pre-existing NEC Terms Service Contract for Pier Maintenance the Contractor has prepared, developed and is implementing a plan for the urgent repair works to to stabilise the existing structure and with the goal of enabling the pier to re-open and to avoid further secondary structural damage or loss to business.
2.1.2. Given the timing of this Committee, Members are asked to note the Financial Implications in this Report and authorise the proposed cost of the urgent stabilisation work to ensure the urgent work can be completed, rather than the Chief Executive rely on the use of the delegated urgency powers within the Scheme of Delegations found at Part 4 of the Councils’ Constitutions.
2.1.3. Members are therefore asked to review the financial implications and full cost of the stabilisation work set out at Paragraph 9; authorise the total cost of the urgent works and specifically to authorise the virements proposed by the Chief Finance Officer and the creation of a contingency fund as set out at paragraph 9.2.3 below. 3. Context
3.1The Incident
Following a report of damage to the pier on a previous high tide, an inspection was undertaken on the 4th October 2024 by the borough’s Engineering Services Team at low tide. A pile was found to be broken and hanging from the structure attached by the supporting tie bars and bull rails. The base of the pile had also been sheared off and moved in the northerly direction
The damage was likely caused by impact from flotsam at high tide, shearing the pile at the base and pushing the pile full circumference off itself resting on the concrete haunching to the base and breaking the pile at mid height causing the upper section to fall.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.