CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Adur District Council / Worthing Borough Council
Joint Strategic Committee, Thursday 6 February 2025 at 6.30pm

Transfer of Adur sec 106 funds to Sussex Police

Approved Committee 1 paper

Joint Strategic Committee approved this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.

ItemJSC/81/23-24

Resolved

That the release of £107,155.06 of s106 funds held by Adur District Council to Sussex Police be approved as detailed in 3.1 onwards and to approve a budget virement of £107,155.06 from S106 monies for Adur District Council, creating a capital budget of the same amount. 2. That the Assistant Director for Regenerative Development be authorised to enter into a Deed of Agreement with Sussex Police to release those funds Call In: The call-in deadline for decisions will be 5.00pm on 18 February 2025
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ Adur District Council secured the obligation for a financial contribution of £104,376.97 (index linked) of s106 funds for Police Services in the s106 legal agreement dated 04/08/2023 under the development AWDM/0323/19 at Land South Of West Street And West Of Loose Lane, Sompting.

1.2.​ £107,155.06 is due to be paid by the end of January 2025. The stipulations of how the s106 funds should be spent are “towards improvements to the Sussex Police Service”.

1.3.​ Sussex Police are requesting the utilisation of s106 funds received by Adur District Council in accordance with section 4.

2.​ Recommendations

The Joint Strategic Committee is recommended to: 2.1.​ Approve the release of £107,155.06 of s106 funds held by Adur District Council to Sussex Police as detailed in 3.1 onwards and to approve a budget virement of £107,155.06 from S106 monies for Adur District Council, creating a capital budget of the same amount.

2.2.​ Authorise the Assistant Director for Regenerative Development to enter into a Deed of Agreement with Sussex Police to release those funds.

3.​ Context

3.1.​ The s106 agreement dated 04/08/2023 under the development AWDM/0323/19 at Land South Of West Street And West Of Loose Lane, Sompting (West Sompting) contained an obligation for the developer to provide a financial contribution of £104,376.97 (index linked) to Adur District Council to be used ‘towards improvements to the Sussex Police Service’.

3.2.​ The payment was due ‘on or before the Occupation of the first (1st) Dwelling’. The payment of £107,155.06 (which was index linked from the date of the agreement) is due to be paid by the end of January 2025. There is a deadline of 10 years from the receipt of a contribution for it to be spent, as stipulated in the s106 agreement.

3.3.​ The legal agreement also covenants ‘the Council to pay the Policing Contribution received under this Deed to Sussex Police or to any successor group which undertakes the same function ("the Group") upon receipt of a document from the Group confirming that it will apply the Contribution for the purpose set out in this Deed and for no other purposes whatsoever and further that it shall refund any unspent portion of the Contribution within ten (10) years of the date was paid to the Council by the Owner.’

3.4.​ The Adur Infrastructure Delivery Plan (IDP) 2016, which was prepared alongside the Adur Local Plan 2017, in section C lists the infrastructure requirements needed to meet the needs generated by the development proposed with the Adur Local Plan and to ensure that infrastructure is properly planned for and delivered in line with the identified requirement. 3.5.​ In relation to the West Sompting development planned for in the Adur Local Plan ‘Improvements to police services’ was included as being essential to meet demand arising from the development. It was noted that this would be funded through developer contributions.

3.6.​ The Planning Committee Report includes the following comments from Sussex Police relating to the application: Advises that the development will place permanent, on-going demands on Sussex Police which cannot be fully shouldered by direct taxation. In order to maintain the current level of policing, developer contributions towards the provision of capital infrastructure will be required. The capital cost of policing new growth as a result of this major planning application equates to £104,376.97, to go towards the cost of additional police officers and support staff, the cost of accommodating additional staff and one additional vehicle.

​ 4.​ Issues for consideration

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transfer of Adur sec 106 funds to Sussex PoliceAgenda 231 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, absent
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

All 13 on the meeting page

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies