Worthing Public Realm - Delivering Montague Gardens

Approved Committee 1 paper

Joint Strategic Committee approved this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.

ItemJSC/84/23-24

Resolved

That the collaboration between WSCC and WBC in the delivery of Montague Gardens be approved, noting WBC responsibility for project management and scheme delivery; supported by the WSCC Growth Deal Officers. 2. That the acceptance of Pooled Business Rates be authorised , £300k funding with up to a further £100k available to underwrite the scheme’s capital budget as required, subject to successful s278 technical approval and traffic regulation order (TRO). 3. That authority be delegated to the Assistant Director for Place & Economy, in consultation with the Cabinet Member for Regeneration, the authority to approve and award a contract for the construction of the public realm project, subject to the outcome of a compliant procurement process. 4. That the increase of £400k to the capital programme budget be approved, funded by Pooled Business Rates funding of £400k. This will bring the budget available to the delivery phase to a total of £3.1m. Call In: The call-in deadline for decisions will be 5.00pm on 18 February 2025
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ The purpose of this report is to provide Members with the opportunity to formally collaborate with West Sussex County Council (WSCC) in the mutually agreed regeneration of Montague Place.

1.2.​ To outline the required capital funding for the development of a new town centre public realm scheme in its place, Montague Gardens.

1.3.​ To ensure that Members are thoroughly informed regarding the WSCC/Growth Deal business rates funding contribution that supports the scheme.

1.4.​ To note the release of previously agreed Worthing Borough Council (WBC) Community Infrastructure Levy funding at £2.7m. 1.5.​ To recognise the importance of Montague Gardens as a key connection to and from the seafront, to the town centre, and therefore a key anchor point as part of a new strategy to support our incredible seafront and to help it thrive into the future.

2.​ Recommendations

2.1.​ The Joint Strategic Committee is recommended to:

2.1.1.​ Approve the collaboration between WSCC and WBC in the delivery of Montague Gardens, noting WBC responsibility for project management and scheme delivery; supported by the WSCC Growth Deal Officers.

2.1.2.​ Authorise the acceptance of Pooled Business Rates, £300k funding with up to a further £100k available to underwrite the scheme’s capital budget as required, subject to successful s278 technical approval and traffic regulation order (TRO).

2.1.3.​ Delegate authority to the Assistant Director for Place & Economy, in consultation with the Cabinet Member for Regeneration, the authority to approve and award a contract for the construction of the public realm project, subject to the outcome of a compliant procurement process.

2.1.4.​ Approve the increase of £400k to the capital programme budget, funded by Pooled Business Rates funding of £400k. This will bring the budget available to the delivery phase to a total of £3.1m.

3.​ Context

3.1.​ The Adur and Worthing Growth Deal (A&WG), signed in March 2017, identified up to 8 public realm schemes aimed at supporting the regeneration of Worthing town centre. The agreed programme included initial funding from WSCC Capital Programme (£5m) with the remainder being sourced through developer contributions, to include Community Infrastructure Levy (CIL); planning obligations (Section 106) and grants and available pooled business rates to support delivery of later phases of the programme.

3.2.​ The delivery of the Worthing Public Realm programme is overseen by an officer and member group, namely the Public Realm Board. The Public Realm Board is a joint WBC and WSCC Board. This programme of public realm delivery was born out of the Worthing Investment Prospectus (2016).

3.3.​ The Montague Place public realm project is the third scheme to move to fruition from the Adur & Worthing Growth Deal (2017). In partnership between WBC and WSCC the two completed schemes are Portland Road and most recently, Railway Approach. Responsibility for the delivery of these projects have alternated between authorities. Worthing Borough Council is delivering the new Montague Place, which has also received a name change for the area to Montague Gardens; a title better suiting the design and desired use of the space.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Worthing Public Realm: Delivering Montague GardensReport 239 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, absent
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Worthing Public Realm - Delivering Montague GardensThis decision
  2. Public Space Protection Orders - Dog Control in Adur and WorthingApproved
  3. Worthing Public Realm - Delivering transformation at Montague PlaceAgreed
  4. Regulating wisely: Updated Adur and Worthing Public Health & Regulation Enforcement PolicyApproved
  5. Outcome of the public consultation in respect of the working age Council Tax Support Scheme for Worthing Borough Council in respect of 2023/24Noted
  6. Council Tax Support Scheme for Worthing Borough Council in respect of 2023/24 - public consultation questionsNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies