That authority be delegated to o the Assistant Director for Place & Economy, in consultation with the Cabinet Member for Environment & Leisure ( Adur ) and Cabinet Member for Communities, Culture & Leisure (Worthing), to progress negotiations on the future leisure contracts for both councils, as follows: a. Should negotiations be successful on the recommended option as detailed in the paper, Officers will seek to confirm contractual arrangements to deliver the negotiated terms against the Councils’ leisure contracts ahead of a key decision b. Should negotiations be unsuccessful then Officers will seek, under the alternative recommendation, to tender the contracts to the market. 2. Based on the outcome of 2.1, it be requested that the Assistant Director Place & Economy bring a further report to the Joint Strategic Committee to agree the new terms and seek the key decision to proceed to award the new leisure contracts for the Councils’ based on either the recommended option (3) or the alternative option (2). Call In: The call-in deadline for decisions will be 5.00pm on 15 April 2025
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. The report outlines the key options for consideration in the context of renewing the Adur Leisure Contract and how this could affect the Worthing Leisure Contract.
1.2. The report clearly articulates these options and the rationale behind each of them, whilst also providing a recommended position in order to proceed with confidence through 2025/26.
1.3. As a result of the paper, Officers will look to negotiate the best position for Worthing and Adur residents through the recommended options which are suggested to be progressed.
2. Recommendations 2.1. That the Committee delegates authority to the Assistant Director for Place & Economy, in consultation with the Cabinet Member for Environment & Leisure (Adur) and Cabinet Member for Communities, Culture & Leisure (Worthing), to progress negotiations on the future leisure contracts for both councils, as follows:
2.1.1. Should negotiations be successful on the recommended option as detailed in the paper, Officers will seek to confirm contractual arrangements to deliver the negotiated terms against the Councils’ leisure contracts ahead of a key decision.
2.1.2. Should negotiations be unsuccessful then Officers will seek, under the alternative recommendation, to tender the contracts to the market.
2.2. Based on the outcome of 2.1, request the Assistant Director Place & Economy bring a further report to the Joint Strategic Committee to agree the new terms and seek the key decision to proceed to award the new leisure contracts for the Councils’ based on either the recommended option or the alternative option.
3. Context
3.1 In 2015 South Downs Leisure (bidding as Worthing Leisure) were appointed to manage all leisure facilities in Worthing under a 25 year contract to 2040. This was following a tender process wherein only a single complaint response was received. The facilities include Worthing Leisure Centre, Splashpoint, Field Place and Palatine Park, the latter under a tripartite agreement with a community sports club.
3.2 On the 16th of July 2020 Adur Community Leisure (ACL) went into administration immediately closing all leisure facilities in Adur. Officers at the time presented this information and options to the Joint strategic committee (JSC) in September 2020 and requested that the committee consider a direct award to South Downs Leisure (SDL) to take on the operation of the Adur Leisure facilities (JSC; November 2020). 3.3 Aligned to 3.2, Members agreed the approach and South Downs Leisure (SDL) were directly awarded a contract to manage all of Adur’s leisure facilities until March 2026 under an emergency provision. The facilities include Lancing Manor Leisure Centre, Southwick Leisure Centre and Wadars Swimming Pool.
3.4 Both the Adur and Worthing leisure contracts are constructed as concession contracts and due to the nature and complexity of this type of legal relationship these can take up to 12 months to complete, therefore a key decision around a chosen procurement method must be made by Spring ‘25 to enable a new contract to be deployed in Adur from April ‘26. More specifically, a procurement, negotiation and re-contracting of this nature pulls on significant resources from legal and procurement in particular, therefore providing as much time as possible if required on the chosen procurement route rather than running multiple options in parallel.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.