That the progress of the WICC be noted and events which have taken place since the last report to the Committee. 2. That the financial paragraphs in this report be noted and an increase of the budget for the project to £45,950,000 be approved to enable the completion of the scheme. 3. That authority be delegated to the Assistant Director, Regenerative Development in consultation with the Cabinet Member for Regeneration, Leader of Worthing Borough Council and Chief Financial Officer to agree to any reasonable costs (within agreed budget at 2.1.2) to ensure the development contract is completed. This will include costs associated with the appointment of any specialist advice to inspect and/or report on the building, as well as associated legal costs required to protect the council's contractual interests to support resolution of issues and occupation of the building. 4. That it be noted that a fully detailed project review report will be presented to the appropriate committee for project scrutiny as soon as practicable following the conclusion of all contract agreements and Worthing Integrated Care Centre occupation. Call In: The call-in deadline for decisions will be 5.00pm on 15 April 2025
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. The report updates Members on the delivery of the Worthing Integrated Care Centre (WICC) and Multi Storey Car Park (MSCP) at Stoke Abbott Road following the Joint Strategic Sub-Committee of 6 February 2024.
1.2. The report also notes the ongoing issues with the water system at the WICC which has delayed occupancy, and outlines the actions and efforts to work with all partners to resolve the issues and ensure the building is fully operational and occupied as soon as possible.
1.3. The report sets out the key factors that have impacted on the construction programme and increased delay costs. The report seeks Member approval to draw down an additional budget and contingency funds to meet any remaining delivery requirements.
2. Recommendations
2.1.1. To note the progress of the WICC and events which have taken place since the last report to the Committee.
2.1.2. To note the financial paragraphs in this report and to approve an increase of the budget for the project to £45,950,000 to enable the completion of the scheme.
2.1.3. To delegate authority to the Assistant Director, Regenerative Development in consultation with the Cabinet Member for Regeneration, Leader of Worthing Borough Council and Chief Financial Officer to agree to any reasonable costs (within agreed budget at 2.1.2) to ensure the development contract is completed. This will include costs associated with the appointment of any specialist advice to inspect and/or report on the building, as well as associated legal costs required to protect the council's contractual interests to support resolution of issues and occupation of the building.
2.1.4. To note that a fully detailed project review report will be presented to the appropriate committee for project scrutiny as soon as practicable following the conclusion of all contract agreements and Worthing Integrated Care Centre occupation.
1. Background
1.1. Members are referred to the background papers attached to this report.
1.2. The last report to Members was taken to the Worthing Joint Strategic Sub-Committee on 6 February 2024. Members agreed the terms of a Settlement Agreement between which had arisen due to delays in the project build. However, despite the ‘Settlement Agreement’ of February 2024 “ensuring practical completion of the WICC and MSCP by May 2024”, by March 2024 further delays were again incurred on the time scales for delivery of the development.
1.3. These delays extended the construction work programme for the WICC and MSCP to 2 August 2024. The contractor was granted extensions of time by the Employers Agent (EA), as per their role, but at no direct additional construction cost to the council. However, as outlined below in this report costs which do not directly arise from the construction continue to be incurred due to delay.
1.4. The EA was appointed by Worthing Borough Council to independently approve and oversee the construction programme and sign-off. The EA’s role is to act on behalf of the client during the construction projects, particularly those using design and build contracts, overseeing project administration, ensuring quality and cost management, and acting as a liaison between the client and the contractor. It is the EA’s role to agree to extensions of time, programme delay, and completion of works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.