Delivery of the Shoreham Flood Defence Project

Noted Committee 1 paper

AI summaryJoint Strategic Committee approves a £949,421 capital budget increase and delegates authority to the Chief Executive to deliver the Shoreham flood defence scheme next to Sussex Yacht Club, with construction due March to September 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNote progress and delegate contract and funding decisions
Money£949,421 capital budget increaseFunded by £816,000 levy, £106,000 Covid grant, £181,000 inflation grant
What happens nextAward construction contractDecember 2025 to February 2026, construction March to September 2026
Who it affectsSt Mary's Ward, ShorehamArea around Sussex Yacht Club, Western Harbour Arm

What was decided

The Committee noted the project update and delegated to the Chief Executive the power to accept £816,000 of additional local levy funding, a £106,000 Covid 19 Grant and a £181,000 Inflation Grant. Report P15, P16, P70, P71

A £949,421 increase to the capital budget was approved, funded by the new grants, and the project will be added to the 2026/27 capital programme with financing costs in Adur and Worthing revenue budgets. Report P17

Authority was delegated to the Chief Executive, in consultation with the Leader and the Cabinet Member for Regeneration and Strategic Planning, to award a construction contract, appoint professional services, agree a S278/38 highways deal with West Sussex County Council, and complete the 25.95m2 land transfer and operating agreements with Sussex Yacht Club. Report P18, P20, P21, P22, P26

Why

The land next to Sussex Yacht Club is a known weak point in Shoreham's flood defences, with the most recent flood event in April 2024, and the Western Harbour Arm remains vulnerable to flooding. Report P28, P61, P63

Detailed design, planning consent and ground investigations are now complete, so the council wants to move quickly to construction before another flood season. Report P44, P63

Additional external funding from Coast to Capital, the Environment Agency and the local Levy has been secured to cover the funding shortfall. Report P70, P71

What happens next

Sussex Yacht Club serves the Deed of Transfer notice from 17 December 2025 into January 2026 and the 25.95m2 land is transferred to the council. Report P56

Officers appoint the most advantageous construction contractor between December 2025 and February 2026 and finalise the construction management plan with Sussex Yacht Club. Report P50, P51, P57

Pre-construction mobilisation runs February to March 2026, followed by a 28-week construction delivery period from March to September 2026, with continuous access to Sussex Yacht Club maintained. Report P58, P59, P90

The money

  • £816,000 Additional local Levy funding committed to the project Report P15, P70
  • £106,000 Covid 19 Grant from the Environment Agency Report P16, P71
  • £181,000 Inflation Grant in Aid from the Environment Agency Report P16, P71
  • £949,421 Increase to the capital budget, funded by the new grants Report P17
  • £2000.00 Minimum materials commitment to local community projects per £250,000.00 of contract value (pro rata) Report P92

Options considered

  • Chosen: Award the construction contract to the most advantageous tenderer and proceed to delivery. Designs are complete, planning consent is in place, and additional funding has been secured to close the funding gap Report P44, P50, P63, P70, P71
  • Rejected: Pursue a formal order to extinguish Restricted Byway RB 3157 (Stows Gap Hard). Objections were raised during consultation and the council instead designed an access gate into the flood defences to protect the right of way Report P39

Implications

  • Financial: A 10% contingency is held on professional fees and a separate 10% contingency on other cost lines, with paving, interceptor and drainage flagged as major cost items. Report P73, P107
  • Legal: The council relies on Section 111 of the Local Government Act 1972, the Local Government (Contracts) Act 1997 and Section 1 of the Localism Act 2011; a S278/38 highways agreement will be needed with West Sussex County Council. Report P22, P76, P77, P78
  • Equalities: DDA-compliant pedestrian access at the western end of the site is being maintained, responding to concerns about alternative routes. Report P90, P96
  • Climate: The scheme protects the coastline from climate change and rising sea levels and will use a permeable Terram Truckpave geocell surface to aid drainage. Report P102
  • Risk: Sussex Yacht Club concerns, restrictive byway delays and cycle path design changes have already extended the programme; further project delay risk is being managed by leaving the WSCC cycle path to a separate project. Report P43, P62, P108

Who and where

  • Residents and businesses in St Mary's Ward, Shoreham, especially around the Western Harbour Arm Report P3, P28, P61
  • Sussex Yacht Club, as landowner, community partner and operator of the new flood defence gates Report P23, P45, P67
  • West Sussex County Council, as the future adopter of the new footway and possible operator of a separate cycle path project Report P22, P30, P108
  • Coast to Capital and the Environment Agency as the main external funders Report P70, P71

Timeline

  • 31 January 2019: JSC agreed purchase of the SYC land strip for the flood defence wall Report P28
  • March 2019: Planning permission for the development granted Report P30
  • November 2021: Adur District Council demolished the redundant yacht club building Report P31
  • April 2024: Most recent flood event in the area Report P28, P61
  • 4 December 2024: WSCC Planning and Rights of Way Committee determined SYC's challenge to the line of RB 3157 Report P40
  • December 2025 to February 2026: Appointment of construction contractor and legal drafting Report P57
  • 9 December 2025: JSC decision to approve budget increase and delegate delivery Report P55
  • 17 December 2025 to January 2026: SYC Notice of Deed of Transfer and 25.95m2 land transfer Report P56
  • February 2026 to March 2026: Pre-construction mobilisation, including six-week construction management plan and test wall Report P58
  • March 2026 to September 2026: 28-week construction delivery period for the flood defences Report P59

Plain English for the jargon

  • RIBA 4: Royal Institute of British Architects Work Stage 4, the detailed design stage
  • S278/38 agreement: A legal agreement under the Highways Act for works to be adopted by the county council as highway
  • Restricted Byway: A public right of way open to walkers, cyclists, horseriders and horse-drawn vehicles but not motor vehicles
  • NEC4 Option A: A priced contract with activity schedule, a fixed-price lump-sum construction contract where the contractor carries most cost risk
  • ADC / SYC / WSCC / MGAC: Adur District Council, Sussex Yacht Club, West Sussex County Council, and the council's quantity surveyor
  • DDA: Disability Discrimination Act, the standard for accessible design
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/80/25-26

Resolved

That the update on the progress of the flood defence development be noted. 2. That authority be delegated to the Chief Executive agreement to accept the additional local levy funding of £816,000 as set out in section 8 of the report. 3. That authority be delegated to the Chief Executive the agreement to accept the additional Covid 19 Grant of £106,000 and Inflation Grant of £181,000 as set out in Item 8.2 of the report. 4. That an increase to the capital budget of £949,421 be approved to be funded by the additional grant funding allocations. 5. That the Chief Executive be authorised in consultation with the Leader and Cabinet Member for Regeneration & Strategic Planning to proceed with the delivery of the flood defence construction programme and subject to the agreed budget envelope as set out in Exempt Appendix 1. addition of the project to the Services capital programme for 2026/27 be approved and the financing costs to be included in the Adur and Worthing revenue budgets. 6. The authority be delegated to the Chief Executive in consultation with the Leader and Cabinet Member for Regeneration & Strategic Planning to: a. Award, execute and enter into a construction contract and any required ancillary agreements after carrying out a compliant procurement process, to enable delivery of the Flood Defence scheme and subject to the cost being within the total approved budget envelope as set out in Exempt Appendix 1. b. Appoint any other necessary professional services to support the flood defence delivery within the agreed budget envelope. c. Enter into any statutorily required agreements with West Sussex County Council to enable the construction and formalisation of a S278/38 agreement to enable the adoption of the proposed footway by the Highways authority on completion of the construction infrastructure by Adur District Council. d. Enter into an agreement with Sussex Yacht Club for the management and operation of the flood defence gates 2 on terms to be agreed with the Regenerative Development and Inward Investment Manager in consultation with the Council’s Safety and Resilience Manager. e. Enter any necessary operational agreements related to the delivery of the flood defences regarding the Contract and Licence to Occupy Sussex Yacht Club land. f. Enter and execute a transfer from Sussex Yacht Club to the Council of a small additional piece of land 25.95m2 referred to in paragraph 4.8 of this report Call In: ... view the full minutes text for item JSC/80/25-26
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Joint Strategic Committee 9 December 2025

Key Decision [Yes]

Ward(s) Affected: St Mary’s

Delivery of the Shoreham Flood Defence Project

Report by the Chief Executive

Officer Contact Details

Phil Graham Regenerative Development and Inward Investment Manager [email protected]

1.​ Purpose

1.1.​ The purpose of this report is to provide the Joint Strategic Committee with an update on the flood defence project in terms of timescales, estimated delivery and process.

1.2.​ The report will seek Member approval to proceed with the delivery of the flood defences adjacent to Sussex Yacht Club in Shoreham.

1.3.​ The report sets out the necessary budget and highlights further external funding that has been secured to deliver the project.

2.​ Recommendations

2.1.​ Joint Strategic Committee is recommended to:

2.1.1.​ Note the update on the progress of the flood defence development.

1 2.1.2.​ Delegate to the Chief Executive agreement to accept the additional local levy funding of £816,000 as set out in section 8 of the report.

2.1.3.​ Delegate to the Chief Executive agreement to accept the additional Covid 19 Grant of £106,000 and Inflation Grant of £181,000 as set out in Item 8.2.

2.1.4.​ Approve an increase to the capital budget of £949,421 to be funded by the additional grant funding allocations.

2.1.5.​ Authorise the Chief Executive in consultation with the Leader and Cabinet Member for Regeneration & Strategic Planning to proceed with the delivery of the flood defence construction programme and subject to the agreed budget envelope as set out in Exempt Appendix 1.

2.1.6.​ Delegate authority to the Chief Executive in consultation with the Leader and Cabinet Member for Regeneration & Strategic Planning to:

a)​ Award, execute and enter into a construction contract and any required ancillary agreements after carrying out a compliant procurement process, to enable delivery of the Flood Defence scheme and subject to the cost being within the total approved budget envelope as set out in Exempt Appendix 1.

b)​ Appoint any other necessary professional services to support the flood defence delivery within the agreed budget envelope.

c)​ Enter into any statutorily required agreements with West Sussex County Council to enable the construction and formalisation of a S278/38 agreement to enable the adoption of the proposed footway by the Highways authority on completion of the construction infrastructure by Adur District Council.

d)​ Enter into an agreement with Sussex Yacht Club for the management and operation of the flood defence gates

2 on terms to be agreed with the Regenerative Development and Inward Investment Manager in consultation with the Council’s Safety and Resilience Manager.

e)​ Enter any necessary operational agreements related to the delivery of the flood defences regarding the Contract and Licence to Occupy Sussex Yacht Club land.

f)​ Enter and execute a transfer from Sussex Yacht Club to the Council of a small additional piece of land 25.95m2 referred to in paragraph 4.8 of this report

3.​ Background

3.1.​ The Joint Strategic Committee on 31 January 2019 agreed to the purchase of a 3.5m wide, 240m long strip of land (adjacent to the A259 on Brighton Road) from Sussex Yacht Club (SYC) by Adur District Council (ADC) to build a new flood defence wall. The land in question had been identified as a key weakness in the flood defences in Shoreham, experiencing a number of flooding events in recent years, impacting investment, growth and regeneration in this area. The area is prone to flooding with the most recent flood event taking place in April 2024.

3.2.​ The capital receipt from the sale of land has been used by SYC to construct their new Yacht Club on the southern side of the existing Clubhouse land which is now complete and operational.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Delivery of the Shoreham Flood Defence ProjectAgenda 634 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SC
Councillor Sophie CoxWorthing Member, present
RG
Councillor Rita GarnerWorthing Member, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, absent
JG
Councillor Jeremy GardnerChair, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonVice-Chair, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

All 13 on the meeting page

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies