AI summaryJoint Strategic Committee notes progress on the Worthing Integrated Care Centre, including ongoing technical issues being resolved, with a full project review to follow completion.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted progress, technical issues, and future review
MoneyNot stated
What happens nextProject review after completionFull review to go to scrutiny committee once practicable
Who it affectsWorthing residents and NHS usersHealthcare services for the wider Worthing area
What was decided
The committee noted the contents of the report on the WICC project, including the progress update and actions being taken to make the centre fully operational as soon as possible.
The committee noted the ongoing technical solutions and the actions being taken by officers to resolve the issues.
The committee noted that a fully detailed project review report will be presented to the appropriate committee for overview and scrutiny after the WICC project is completed.
Why
The report sets out the economic, social, equality, community safety, human rights, environmental, governance and sustainability aspects of the WICC project for the committee's awareness. Report P3, P4, P6, P9, 2.3, 2.4, P18, P19, P21
What happens next
A fully detailed project review of the WICC will be presented to the appropriate committee for overview and scrutiny as soon as practicable after project completion.
Officers continue to work on the technical solutions needed to make the centre fully operational, with updates shared with the Cabinet Member for Regeneration, the Leader of the Council and at project board meetings. Report P19, P24
The call-in deadline for this decision is 5.00pm on 19 December 2025.
Options considered
Chosen: Note the report, the technical issues being addressed, and a future project review. This was the only option put to the committee
Implications
Equalities: Bringing services under one roof is expected to improve access for people with mobility impairments, older adults, people with chronic conditions needing multiple specialists, and homeless populations. Report P9, P10, P11, 2.4
Climate: Sustainability features include a target of BREEAM certification, 20% electric vehicle charging points, solar panels, air source heat pumps, underfloor heating, cycle parking and pool cars. Report P21, P22
Staffing: Construction has created local employment, and the centre's operation is expected to create ongoing jobs for healthcare professionals, administrative staff and support personnel. Report P4
Risk: There are ongoing technical solutions to resolve before the centre is fully operational, and the report does not set out the nature of these issues.
Other: The centre is expected to increase town centre footfall, supporting local shops, restaurants and other services and contributing to town centre regeneration. Report P4
Who and where
Worthing residents and NHS service users, including GP, dental, mental health and pharmacy patients Report P6
People with mobility impairments, older adults and people with chronic conditions needing multiple specialists Report P10
9th June 2020: Joint Strategic Committee considered the procurement approach for the WICC development Report P1
After project completion: A fully detailed project review report will be presented to the appropriate committee
30th March 2021: Report on delivery of the WICC and MSCP on Worthing Town Hall Car Park Report P1
13th June 2023: Joint Strategic Sub-Committee agenda item 11 on the WICC project Report P1
6th February 2024: Joint Strategic Sub-Committee meeting on the WICC project Report P1
8th July 2025: Previous update on the Worthing Integrated Care Centre Report P1
5.00pm on 19 December 2025: Call-in deadline for the decision
Plain English for the jargon
WICC: Worthing Integrated Care Centre
BREEAM: A recognised standard for assessing the environmental sustainability of buildings
EPC: Energy Performance Certificate, showing the energy efficiency of a building
WSWL: Used in the report as a project partner, with no definition given in the supplied text
MSCP: Multi-Storey Car Park, built adjacent to the care centre
CIL: Community Infrastructure Levy
IIP: Infrastructure Investment Plan
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/79/25-26
Resolved
That the contents of this report be noted including the update on progress and the actions being taken to ensure the Worthing Integrated Care Centre is fully operational as soon as possible. 2. That the ongoing technical solutions surrounding the WICC project and the actions being taken by Officers to resolve the issues be noted. 3. That it be noted that as soon as practicable after completion of the WICC project, a fully detailed project review report will be presented to the appropriate committee for overview and scrutiny of the project. Call In: The call-in deadline for decisions will be 5.00pm on 19 December 2025
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
Title: Worthing Integrated Care Centre Update Report
Report by: Phil Graham, Regenerative Development and Inward Investment Manager
1. Purpose
1.1. The purpose of this report is to provide the Joint Strategic Committee with an update on the delivery of the Worthing Integrated Care Centre (WICC) and Civic Quarter multi-storey car park (MSCP) following the previous update provided on 8th July 2025.
1.2. This report outlines the technical issues specifically regarding the water management system.This has caused delay to the operational opening of the WICC building, creating commercial issues to be resolved between our partners and stakeholders as well as the developer and contractor.
1.3. The report advises on the current position with our partners and stakeholders; actions being taken by the council to mitigate impacts as well as updating on the defect management strategy.
2. Recommendations The Joint Strategic Committee is recommended to:
2.1. Note the contents of this report, the update on progress and the actions being taken to ensure the Worthing Integrated Care Centre is fully operational as soon as possible.
1 2.2. To note the ongoing technical solutions surrounding the WICC project and the actions being taken by Officers to resolve the issues.
2.3. To note that as soon as practicable after completion of the WICC project, a fully detailed project review report will be presented to the appropriate committee for overview and scrutiny of the project.
3. Background
3.1. A previous report presented on 8th July 2025 set out the background regarding project delays for the WICC and MSCP and this report is referenced in the background papers.
3.2. Sectional Completion for the WICC and MSCP was issued by the Employer’s Agent who was appointed by West Sussex (Worthing) Limited (WSWL) and was responsible for signing off the buildings on 3rd December 2024, at which point the buildings were handed over to the council. Savills were appointed to provide managing agent and facility management services, commencing at the point of Sectional Completion.
3.3. Legionella and Water System Issues:
Prior to Sectional Completion, Savills’ undertook their own due diligence water sample testing on 22 October 2024.The laboratory results from these samples, received on 2nd November 2024, showed traces of Legionella bacteria had been identified. Following this, the construction contractor, Galliford Try (GT) then undertook their own sample testing on 6 November 2024 and advised the council on 27th November 2024 that they had recorded further positive Legionella results.
At this point the contractor proposed and agreed a hybrid approach to water sampling in terms of lateral flow rapid tests as well as compliant laboratory testing (that can take up to 14 days) with WSWL and the Employers Agent (EA). The EA then signed off the building as ready for beneficial occupation on 3rd December 2024 whilst awaiting for the formal laboratory results to be confirmed on 13 December 2024.
2 Despite these results being negative on 13th December 2024, further sampling undertaken by Savills on 9 December 2024 confirmed the presence of Legionella in the water system on 23rd December 2024. The council raised their concerns immediately with WSWL and the contractor, and initiated its own specialist assessments to investigate the issues.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.