Investment in Bus Shelters across Worthing Borough
AgreedCommittee1 paper
AI summaryAdur and Worthing Joint Strategic Committee accepted a grant of approximately £240,000 from West Sussex County Council to upgrade 13 to 15 bus shelters in Worthing, notably on Marine Parade.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedService Director for Place and Economy authorised to act
Moneyapproximately £240,000External grant from West Sussex County Council, no borrowing required
What happens nextProcurement and installationShelters expected to be installed between September and December 2026
Who it affectsBus users in WorthingUpgrades focus on Marine Parade hub and borough-wide shelters
What was decided
Accepted the grant funding offer from West Sussex County Council and approved a provisional capital budget set at the amount of the grant received. Report P9, P42
Delegated authority to the Service Director for Place and Economy to enter into the Grant Agreement with West Sussex County Council and to work in partnership to upgrade bus shelters. Report P7
Delegated authority to the Service Director for Place and Economy, in consultation with the Cabinet Member for Regeneration, to enter into contracts for capital works subject to a compliant procurement process and available budget. Report P8
Why
The borough's bus shelter stock is over 30 years old and in deteriorated condition, with seafront shelters in the worst state, while Marine Parade is identified as Worthing's main bus interchange. Report P15, P21, P23
The project supports the council's Fair, Green and Local corporate plan and the Place Regeneration and Economic Growth Mission, including possible use of living roofs on a nature corridor. Report P18
The proposal is expected to be fully externally funded, requiring no borrowing, though officer time will be needed as Worthing Borough Council acts as lead authority. Report P40
What happens next
A procurement strategy will be developed and a compliant procurement process run, with final locations and designs shared with the Cabinet Member for Regeneration before orders are placed. Report P8, P33
Bus stops may need to be temporarily moved during works, with bus users informed in advance in partnership with operators. Report P37
The project will be overseen by a Project Delivery Group and governed by the council's Regeneration and Economic Growth Mission Board. Report P58
The money
approximately £240,000 Expected WSCC grant to fund 13 to 15 shelter upgrades or new installations Report P32, P40
£8,000 and £15,500 Average cost per bus shelter including installation, electrical connections allowed for separately Report P32
more than £9m Department for Transport grant awarded to West Sussex County Council for bus network improvements Report P11
over £19 million Total BSIP funding received by WSCC from the Department for Transport since 2022 Report P13
Implications
Financial: Project is externally funded in full, with no borrowing required; new shelters will become a Worthing Borough Council asset and may reduce maintenance obligations. Report P40, P41, P42
Legal: Procurement must comply with the council's Contract Standing Orders and the Procurement Act 2023; powers relied on include Section 111 Local Government Act 1972, s1 Localism Act 2011, s139 Local Government Act 1972, s1 Local Government (Contracts) Act 1997 and Section 3(1) Local Government Act 1999. Report P45, P46, P47, P48, P49
Equalities: Replaced shelters will include various seating options and spaces for wheeled carriages, with reactive lighting at high-use main hub shelters to improve safety and accessibility. Report P52, 2.2, P55
Climate: Proposal has the potential to incorporate sedum green living roofs to improve shading and pollinator routes along the seafront nature corridor. Report P18, P30, P57
Risk: The Marine Parade shelters are in a conservation area, requiring a planning application, and Bauer Outdoor Media UK was unable to take on additional shelters, increasing delivery risk for the council. Report P26, P41
Who and where
Bus passengers in Worthing, particularly users of routes 5, 10, 700, pulse and the new 701 route Report P14
Worthing Business Improvement District, which provided a letter of support for the grant Report P35
Bus operators including Stagecoach, with engagement on need and expectations Report P37
Bauer Outdoor Media UK, which holds advertising rights on 55 of the 108 borough shelters under an agreement ending in 2029 Report P16, P17
Timeline
16th June 2026: Next Bus Partnership quarterly forum meeting Report P19
5.00pm on 19 June 2026: Call-in deadline for the decision
September - December '26: Target window for installation of new bus shelters; lead time can be up to 16 weeks Report P33
Plain English for the jargon
BSIP: Bus Service Improvement Plan, the Department for Transport funded programme to improve bus services in West Sussex
WSCC: West Sussex County Council, the upper-tier authority awarding the grant
WBC: Worthing Borough Council, the council accepting the grant and leading delivery
BID: Business Improvement District, a local business levy group that supported the bid
DfT: Department for Transport, the source of the underlying BSIP funding
Living roof: A roof planted with vegetation such as sedum, proposed for the Marine Parade shelters
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/8/26-27
Resolved
That the Service Director for Place and Economy be delegated authority to enter into the Grant Agreement with West Sussex County Council (WSCC), as part of their Bus Service Improvement Plan (BSIP), and work in partnership to upgrade a number of bus shelters across Worthing. 2. That authority be delegated to the Service Director for Place and Economy, to enter into contracts for various elements of the capital works, in consultation with the Cabinet Member for Regeneration, subject to the development of a procurement strategy, the outcome of a compliant procurement process and the award being within the available budget. 3. That the grant funding offer from WSCC be accepted and the creation of a provisional capital budget be approved as detailed in 6.4 of the report and it be noted that the final budget will be set at the amount of the grant received. Call In: The call-in deadline for decisions will be 5.00pm on 19 June 2026.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. The purpose of this report is to outline to Members the opportunity to deliver improvements to a series of bus shelters in Worthing, notably on Marine Parade, through external funding from West Sussex County Council.
1.2. To inform Members of the Grant Funding Agreement and any implications and / or restrictions that need to be highlighted, the outcomes and outputs required through delivery and the funding available to be drawn down.
1.3. To present the beneficial impact the project will have to the town and its sustainable transport credentials.
1.4. To present the rationale for Worthing Borough Council (WBC) to accept the grant funding offer, and work in partnership with West Sussex County Council to deliver the project and assume delegated authority for the project delivery and expenditure of grant funding. 2. Recommendations
The Joint Strategic Committee is recommended:
2.1. To authorise the Service Director for Place and Economy to enter into the Grant Agreement with West Sussex County Council (WSCC), as part of their Bus Service Improvement Plan (BSIP), and work in partnership to upgrade a number of bus shelters across Worthing.
2.2. To authorise the Service Director for Place and Economy a delegated authority to enter into contracts for various elements of the capital works, in consultation with the Cabinet Member for Regeneration, subject to the development of a procurement strategy, the outcome of a compliant procurement process and the award being within the available budget.
2.3. To accept the grant funding offer from WSCC and to approve the creation of a provisional capital budget as detailed in 6.4 of the report and to note that the final budget will be set at the amount of the grant received.
3. Context
3.1 West Sussex County Council (WSCC) has been awarded a grant from the Department for Transport of more than £9m to continue to improve the bus network in the county.
3.2 WSCC formed an Enhanced Partnership with local bus operators in 2021. The partnership was established to deliver countywide bus service recovery and improvements in line with the Bus Back Better National Bus Strategy for England. The partnership developed the Bus Service Improvement Plan (BSIP) to improve bus services in West Sussex and reverse the Covid related shift in journeys away from public transport and encourage passengers back to bus travel.
3.3 Since the submission of the council’s Bus Service Improvement Plan (BSIP) in 2022, the county council has received over £19 million in BSIP funding from the Department for Transport (DfT) to support the council’s BSIP priorities. This grant allowed the county council to launch bus initiatives that benefitted residents through an improved public transport network. These initiatives include new bus lanes, improvements to bus stops and roadside infrastructure, increased bus frequencies, cheaper bus fares for young people, and the introduction of an on-demand bus rideshare service. A number of these initiatives have benefited Worthing residents.
3.4 The Worthing bus network has undergone significant changes in 2025 through an Enhanced Partnership between West Sussex County Council and bus operators, aimed at improving reliability, punctuality and increasing capacity specifically affecting routes 5, 10, 700 and pulse and a new 701 route.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.