CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Adur District Council / Worthing Borough Council
Joint Strategic Committee, Tuesday 9 June 2026 at 6.30pm

Worthing Integrated Care Centre Updates

Noted Committee 1 paper

AI summaryJoint Strategic Committee approves £2.42m capital budget increase for Worthing Integrated Care Centre, taking total to £48.945m, and appoints Bellrock as managing agent, but a new positive legionella test delays water system handover.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedWater system handover still on hold after new test
Money£2,420,310 increase to £48.945mFunded by borrowing, plus property risk reserve for revenue shortfall
What happens nextFurther report to July 2026 committeeContractor response awaited; legal remedies under review
Who it affectsNHS tenants and WICC stakeholdersPlus contractor Galliford Try and developer WSWL

What was decided

Members noted the report and the technical rectifications being applied to the water system by the contractor before handback to the council. Report P4

Members approved a £2,420,310 increase in the capital budget, funded by borrowing, raising the total to £48.945m, with the property risk reserve available to mitigate 2026/27 revenue shortfalls. Report P5, P44, P49

The Service Director for Place and Economy, in consultation with the Leader of Worthing Borough Council, was authorised to finalise Bellrock's appointment as managing agent and facility manager and to sign the property management agreement, with delegation also given to appoint legal and consultancy support. Report P6, 2.5

Why

Design and installation failures in the water system, including an undersized pump, unlagged pipework, dead legs and missing thermal actuators, have repeatedly delayed handback and pushed up costs. Report P11, P12, P13

The contractor took back full responsibility for the water system in August 2025, but the council's own tests on 28 May 2026 returned positive for legionella in specific locations, requiring further action. Report P10, P16

The existing managing agent Savills no longer intends to manage a facility of this nature, prompting a switch to Bellrock, appointed through a framework agreement for an initial three year term. Report P23, P24, P25

What happens next

The contractor will be asked to carry out its own immediate testing and checks, after which the council will decide next steps in consultation with the Leader and report back to the July 2026 committee. Report P17, P18, P20

Options for legal redress, including the existing liquidated damages demand against developer WSWL, will be developed and reported to the committee in July. Report P21

A detailed project review report will be presented to the Joint Overview and Scrutiny Committee after project issues are resolved. Report P31

The money

  • £2,420,310 Increase in capital budget funded by borrowing Report P5, P44
  • £48,945,000 Revised total capital budget for the project Report P49
  • £46,524,690 Current approved capital budget before the increase Report P45
  • -£32,015 Remaining current budget based on estimated commitments Report P46
  • £2,202,325 2025/26 capitalised interest on borrowing Report P47
  • £250,000 Additional capital contingency proposed Report P48

Options considered

  • Chosen: Increase the capital budget by £2,420,310 to £48.945m via borrowing, with property risk reserve cover for revenue shortfalls. Continued delay and capitalised interest have raised the funding requirement Report P5, P43, P44
  • Chosen: Appoint Bellrock as managing agent and facility manager for an initial three year term through a framework agreement. Savills no longer intends to manage a facility of this nature; Bellrock is already working with Savills on transition Report P23, P24, P25
  • Chosen: Delegate authority to the Service Director for Place and Economy to appoint legal and consultancy support within authorised budget. Required to complete delivery of WICC and pursue redress Report 2.5

Implications

  • Financial: Projected revenue break-even point extended from 26 to 35 years of full operation due to higher costs, delayed completion and higher prudential interest rates. Report P63
  • Financial: Revenue shortfall against the 2026/27 budget will need to be managed through the Property Risk Reserve. Report P64
  • Legal: Liquidated damages demand already raised against WSWL under the Development Agreement, with all legal remedies reserved; further options to be reported in July. Report P21
  • Legal: Powers cited include Section 111 Local Government Act 1972, s1 Localism Act 2011, s3(1) Local Government Act 1999 and s1 Local Government (Contracts) Act 1997. Report P67, P68, P69, P70
  • Risk: A new positive legionella result on 28 May 2026 has thrown the planned early June 2026 handback into doubt and triggered further testing and specialist advice. Report P14, P16, P20
  • Staffing: Initial three year appointment of Bellrock is intended to embed operational management, service charge procedures and service standards before any future re-tender. Report P25, P26, P27

Who and where

  • Worthing Borough Council as project owner and eventual building operator Report P4, P9
  • NHS tenants and healthcare service users of the WICC Report P29, P77
  • Contractor Galliford Try, responsible for water system rectification Report P2, P10, P16
  • Developer West Sussex Worthing Limited (WSWL) Report P17, P21
  • Savills (current property management support) and incoming managing agent Bellrock Ltd Report P23, P24

Timeline

  • October 2017: Original budget of £262,000 approved for initial studies Report P35
  • November 2019: Budget increased to £600,000 to progress full business case Report P36
  • March 2021: Full budget of £33.971m approved for construction Report P37
  • June 2023: Budget increased to £39.601m to fund inflationary pressures and construction risks Report P38
  • February 2024: Budget increased to £42.422m following contractor/WSWL dispute Report P39
  • April 2025: Budget increased to £45.950m for further project costs Report P40
  • July 2025: Budget increased to £46.525m to bring the building into operation Report P41
  • August 2025: Contractor took back full responsibility for water system rectification Report P10
  • 28 November 2025: Original target date for compliant water system handback Report P13
  • 9 December 2025: Previous update report to Joint Strategic Committee Report P9
  • 28th May 2026: Council's own water tests returned positive for legionella in specific locations Report P16
  • Early June 2026: Contractor was working toward water system handback before new test result Report P14
  • 9 June 2026: Joint Strategic Committee approves budget increase and Bellrock appointment
  • 5.00pm on 19 June 2026: Call-in deadline for the decision
  • July 2026: Further detailed report to Joint Strategic Committee on water system next steps and legal options Report P18, P20, P21

Plain English for the jargon

  • WICC: Worthing Integrated Care Centre, the healthcare facility under construction
  • WSWL: West Sussex Worthing Limited, the developer under the Development Agreement
  • Legionella: Bacteria that can grow in building water systems and cause Legionnaires' disease; subject of the positive test on 28 May 2026
  • Liquidated damages: A pre-agreed sum claimed for breach of contract, here being pursued against WSWL for delays
  • Property Risk Reserve: Council reserve held to mitigate in-year volatility in property portfolio performance, proposed to cover 2026/27 revenue shortfalls
  • PMA: Property Management Agreement, the contract to be entered into with Bellrock
  • BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability certification standard
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/10/26-27

Resolved

That the contents of the report be noted including the actions relating to the technical rectifications being applied to the water system by the Contractor to ensure it is accepted and handed back to Worthing Borough Council only when safe and compliant. 2. That an increase of the capital budget be approved to be funded by way of borrowing for the project by £2,420,310 to £48.945m as detailed in the Finance Section of the attached report and, to that funding from the property risk reserve may be used to mitigate shortfalls against the 2026/27 revenue budget. This will be subject to further reporting at the point of utilisation. 3. That the Service Director for Place and Economy be authorised, in consultation with the Leader of Worthing Borough Council (and Cabinet Member for Economy & Regeneration), to finalise the terms of appointment for Bellrock Managing Agent and Facility Manager for the WICC for the reasons set out at Item 5 of this Report, and enter into the Property Management Agreement required to secure Bellrock’s services. 4. That authority be delegated to the Service Director for Place & Economy to appoint any necessary legal or consultancy services required to complete the delivery of WICC and seek redress providing the appointments are within the authorised budget. Call In: The call-in deadline for decisions will be 5.00pm on 19 June 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ This report updates Members on:- ●​ The technical works that have been ongoing to rectify the water system undertaken by the design and build construction contractor Galliford Try (the Contractor) in the Worthing Integrated Care Centre (WICC). ●​ The anticipated timeline for handback of the water system by the Contractor in early June 2026. ●​ The results of a recent positive Legionella test taken by the Council and to advise that an updated report on the Council’s next steps will be brought to the July Committee. ●​ An update to the capital budget arising from additional costs prior to handback of the water system to the Council.

The report also sets out the current position on the management of the WICC building and proposed appointment of Bellrock to act as the new long term Managing Agent and Facility Manager for the building. 2.​ Recommendations​ ​ The Joint Strategic Committee is recommended to:

2.1.​ Note the contents of this report and the actions relating to the technical rectifications being applied to the water system by the Contractor to ensure it is accepted and handed back to Worthing Borough Council only when safe and compliant.

2.2.​ Approve an increase of the capital budget to be funded by way of borrowing for the project by £2,420,310 to £48.945m as detailed in the Finance Section of this Report and, to that funding from the property risk reserve may be used to mitigate shortfalls against the 2026/27 revenue budget. This will be subject to further reporting at the point of utilisation.

2.3.​ To authorise the Service Director for Place and Economy, in consultation with the Leader of Worthing Borough Council (and Cabinet Member for Economy & Regeneration), to finalise the terms of appointment for Bellrock Managing Agent and Facility Manager for the WICC for the reasons set out at Item 5 of this Report, and enter into the Property Management Agreement required to secure Bellrock’s services.

2.5To delegate authority to the Service Director for Place and Economy to appoint any necessary legal or consultancy services required to complete the delivery of WICC and seek redress providing the appointments are within the authorised budget.

3.​ Background

3.1.​ A report presented to Worthing Joint Strategic Committee on 9 December 2025 provided an update to the committee on progress of the Worthing Integrated Care Centre and the technical work to resolve outstanding issues that exist at the WICC. In particular, issues with the water management system and the presence of legionella that the Contractor is considered responsible for rectifying, whether arising because of defects in design or in construction or both. Members will be familiar with the history of this matter having regard to previous Reports to this committee which are listed in your background papers.

3.2.​ Members will be aware that in an unusual move post-handover, and as a result of persistent scrutiny and oversight by the Council, including significant independent evidence gathering, the Contractor agreed to take back full responsibility for the rectification of the water system in August 2025 on terms which necessarily required the Contractor to manage the water system as well.

3.3.​ Investigations identified several key failures in the design and installation of the water system, including:​

○​ Insufficient water pump capacity, which required the installation of a new, larger pump. ○​ Unlagged pipework and poor alignment of hot and cold water pipes, causing improper heat transfer. ○​ The presence of "dead legs" (stagnant water sections) and missing thermal actuators and monitoring sensors​

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Worthing Integrated Care Centre UpdatesAgenda 265 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
JG
Councillor Jeremy GardnerAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
LC
Councillor Lee CowenAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AL
Councillor Adrienne LoweAdur Member, present
CB
Councillor Caroline BaxterChair, present
JT
Councillor John TurleyVice-Chair, present
SC
Councillor Sophie CoxWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
MM
Councillor Martin McCabeWorthing Member, present

On this subject at Adur & Worthing

Search all
  1. Worthing Integrated Care Centre UpdatesThis decision
  2. Worthing Integrated Care Centre UpdatesNoted
  3. Worthing Integrated Care Centre: UpdateNoted
  4. Update on the Worthing Integrated Care CentreNoted
  5. Update on Worthing Integrated Care Centre and Multi Storey Car ParkNoted
  6. Worthing Integrated Care Centre ProjectApproved

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies