Policy & Resources Committee, Thursday 8 June 2000 at 11.00am

FLOOD PREVENTION AND LAND DRAINAGE (SCOTLAND) ACT 1997

Agreed Committee 1 paper

Policy & Resources Committee agreed this item on Thursday 8 June 2000. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

Agreed to note the progress to date on the Flood Prevention Scheme. 2. Approved the strategy for progressing future Flood Prevention Schemes. 3. Noted the report from Bute and Cowal Area Committee. (Reference – Report by Director of Transportation and Property dated 10 May 2000 and recommendation by the Bute and Cowal Area Committee and Report by Director of Transportation and Property to that Committee, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy & Resources Committee

Summary

The purpose of this Report is to update Members on the current position regarding the Council’s Flood Prevention Programme and to approve the strategy for progressing future schemes.

Recommendation

The Committee is asked to:

1) note the progress to date on flood prevention scheme. 2) approve the strategy for progressing fbture flood prevention schemes. 3) note the Report from the Bute & Cowal Area Committee.

Background

Reference is made to the report to the Transportation & Property Committee on 10 November 1999 which detailed progress to date and sought approval for the proposals for flood prevention schemes for the 1999/00 financial year.

The enclosed report9ummarises the difficulties that have arisen during the first year of managing the flood prevention programme and sets out a strategy for fbture years.

4. CURRF,NT POSITION

4.1Early in the 1999/2000 financial year, each Area Manager was asked to supply a list of flooding incidents in their area with indications of severity and priority for inclusion as a flood prevent scheme. At that time, the Council’s budget was &250,000 and, with expected 50% grants from the Scottish Executive, it had been hoped to achieve a gross annual budget of between &300,000and $350,000.However, early indications from the Scottish Executive were that schemes to protect only private property wouId have difficulty in producing a positive cost benefit and were therefore unlikely to attract grant aid. There are currently 40 schemes of this type throughout Argyll and Bute. This fact, combined with a cut in the Capital Budget in mid-1999, meant that the effective budget for 1999/00 was &231,000.

C:\WTNDOWS\TEhdP\ra1535-2.doc 1 Q May 2000 4.2 - 244 In order to use this money as effectively as possible, effort was concentrated on high priority schemes between &50,000 and 2100,000, which could be fbnded entirely from within the Council's budget. A report on this basis was submitted to the Transportation Committee on 1O* November 1999 and three schemes were approved for construction, namely: Birch Lodge, Innellan - &90,000 The Avenue, Inveraray - 275,000 Glenarn Road, Rhu - 25 0,O 00 In addition to the above works, a consultant was appointed to undertake a study into the flooding problems at Rothesay at a cost of 215,000. Construction of the three schemes and the consultants study was completed by 3 Is' March 2000.

S. FUTURE STRATEGY

5.2.1 The Scottish Executive has stated that they would expect that each Council would promote flood prevention schemes on the basis of value-for-money with each scheme achieving a positive cost-benefit factor. It is however difficult to obtain a positive cost benefit on schemes where only a small number of residential properties are protected as the capital cost of construction is larger than the money saved annually on flood damage repair costs. While the three schemes built during 1999/00 did not have a positive cost-benefit, they were considered as a high priority in terms of the inconvenience caused by flooding at these locations.

5.2.2 It would appear however that larger schemes, where a mix of commercial, industrial and residential property is to be protected, would have a better chance of attracting grant aid. It would be the intention therefore to complete a design for several of the larger schemes early in the 2000/01 financial year and to submit a grant application to the Scottish Executive. The grant processing can however take up to 9 months and therefore monies would only be available for 2001102 or subsequent years.

5.2.3 The schemes being considered, in order of provisional estimates of cost benefit and likelihood of attracting grant, are: 0 - (a) Antrim View, Islay Estimated Cost f.100,000

Good mix of industrial and residential property.

jb) Black Lynn, Oban Estimated Cost &400,000

Good mix of commercial and residential property

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FLOOD PREVENTION AND LAND DRAINAGE (SCOTLAND) ACT 1997Report 421 KB DownloadRead as text

At this meeting

Whole meeting
2MINUTESAgreed 3REVENUE BUDGET PREPARATION 2001/2002Decided 4RENEWAL AND REPAIRS FUND - SPEND TO SAVEApproved 5TEMPORARY ACCOUNTANTSApproved 6ANNUAL TREASURY MANAGEMENT REPORTAgreed 7DEBT RESCHEDULINGNoted 8PROPERTY VALUATIONS 1999/2000Noted 9CORPORATE POLICY - SUPPLEMENTARY ESTIMATEApproved 10ESTABLISHMENT OF AN AUDIT COMMITTEEAgreed 11LOCAL TAX COLLECTION: PERFORMANCE AT 31 MARCH 2000Noted 12NON-DOMESTIC RATES BEST VALUE SERVICE REVIEWAgreed 13COUNCIL TAX COLLECTION: IMPROVEMENT INITIATIVESNoted 14CAPITAL PROGRAMME 1999/2000 - OUTTURN REPORTNoted 153 YEAR CAPITAL PROGRAMME - FEASIBILITY STUDIESApproved 16CORPORATE RESPONSE TO STEPHEN LAWRENCE INQUIRY (THE MacPHERSON REPORT)Noted 17INTRODUCTION OF 38 HOUR WORKING WEEK: OVERTIME AND BONUS CALCULATORAgreed 18ABSENCE MONITORING FIGURES - APRIL 1999 - MARCH 2000Agreed 19DISCIPLINARY PROCEDURESAgreed 20BEST VALUE APPROACHAgreed 21STRATEGIC PRIORITY: OUTTURNS AND TARGETSAgreed 22ENTITLEMENT OF FOOTWEAR AND CLOTHING GRANTAgreed 23INFORMATION SECURITY MANAGEMENTApproved 24SCOTTISH TOURIST BOARD MEMBERSHIPAgreed 25GLASGOW AIRPORT CONSULTATIVE DOCUMENT - LOCAL AUTHORITY REPRESENTATIONAgreed 26COSLA: URBAN AND RURAL AFFAIRS MEMBERS NETWORKAgreed 27THREE YEAR CAPITAL PLAN 2000/2003 - CCTV SCHEMES - CAMPBELTOWN, HELENSBURGH AND DUNOONAgreed 28GAELIC IN THE COMMUNITY SCHEMEAgreed 29BUS SERVICES SUB COMMITTEEAgreed 30CONTAMINATED LAND - A NEW STATUTORY DUTYAgreed 31RATES RELIEF FOR PHARMACIES AND TOURIST INFORMATION CENTRESAgreed 32LOCH LOMOND INTERIM COMMITTEE - CAPITAL PROGRAMME 2000/2001Agreed 33HOUSING MANAGEMENT SERVICE: STAFFINGAgreed 34CHILDREN'S SERVICE DEVELOPMENT FUND: STAFFINGAgreed
35FLOOD PREVENTION AND LAND DRAINAGE (SCOTLAND) ACT 1997This decision
36PROPOSED DISPOSAL/LEASE OF GROUND AT BLAIRVADACH, SHANDONDecided 37PROPOSED SALE OF CARDROSS ASSEMSSMENT OF CENTRE - CITY OF GLASGOW COUNCILAgreed 40The Committee resolved in terms ofOn the agenda 38CARE PLAN FOR A QUADRIPLEGIC SERIVCE USERPrivate 39BUSINESS/EUROPEAN UNIT, ROTHESAYPrivate 40NORTH PIER, OBAN - DEVELOPMENT PROPOSALSPrivate 41LEASE OF ADDITIONAL OFFICE ACCOMMODATION 64A JOHN STREET, HELENSBURGHPrivate 42WINTER GARDEN VISITORS CENTRE LTD, ROTHESAYPrivate

Who was there

0 of 26 attended
AM
Councillor Allan MacaskillMember, expected
AM
Councillor Archie McCallumMember, expected
CC
Councillor Campbell CameronMember, expected
DW
Councillor David WebsterMember, expected
DC
Councillor Douglas CurrieMember, expected
DM
Councillor Dugie MacKinnonMember, expected
EM
Councillor Elspeth McTaggartMember, expected
JS
Councillor John StirlingMember, expected
MS
Councillor Moyra StewartMember, expected
PC
Councillor Paul ColeshillMember, expected
RB
Councillor Robin BanksMember, expected
RK
Councillor Ronald KinlochMember, expected

All 26 on the meeting page

On this subject at Argyll and Bute

Search all
  1. FLOOD PREVENTION AND LAND DRAINAGE (SCOTLAND) ACT 1997This decision
  2. Campbeltown flood prevention schemeNoted
  3. Campbeltown flood prevention schemeAgreed
  4. Verbal update on Milton Burn Flood Prevention SchemeNoted
  5. Verbal update on the Milton Burn Flood Prevention SchemeNoted
  6. Milton Burn Flood Prevention SchemeNoted

More from Argyll and Bute Policy & Resources Committee

All decisions
MeetingDecisionOutcome
15 Feb 2001 Revenue budget 2001/2002Decision The motion was carried by 12 votes to 9 and accordingly the Committee agreed to recommend to the Council:- 1... Agreed Open
15 Feb 2001 Housing revenue budget 2001/2002: proposals for rent increaseDecision To recommend to the Council – 1. That the rents of Council houses be increase by an average of £1.75 per wee... Decided Open
31 Jan 2001 Revenue budget 2001/2002Decision To recommend:- 1. Approval of the draft Revenue Estimates for this Committee’s Services for 2001/2. 2. To no... Approved Open
21 Dec 2000 Service plansDecision 1. That Members offer any responses to the Chief Executive/respective Directors within 28 days. 2. To remit ... Decided Open
21 Dec 2000 Shaw awardDecision The Committee agreed to offer congratulations to the staff of Personnel Services on their achievement. (Refe... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies