TEMPORARY ACCOUNTANTS

Approved Committee 1 paper

Policy & Resources Committee approved this item on Thursday 8 June 2000. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Approved the virement of £46,313 from Loan Charges to Accounting Section staff costs. (Reference – Report by Director of Finance dated 27 April 2000, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy & Resources Committee

Summary

1.1There are currently 4 accountants within the Finance Department appointcd on temporary contracts. Thcre is a requirement to extend the Contracts for a furthcr period of 6 months. Owing to the additional costs of recruiting temporary staff this will require additional budget to bc made available in respect of cmployee costs within the Accounting Section in the sum of &46,313.OO. This cost can be met from virement from loan charges where savings of &47,148,referred to in the report on debt rescheduling at agenda item 6, are anticipated.

2. FUXOMMENDATIONS

2.1Policy and Kcsources Committee approve the vircment of &46,313.00 from Loan Charges to Accounting Section staff costs.

3. DETAIL

3.1In December 1999 there were 4 vacant posts for professionally qualified accountants. Given the difficulties in recruiting professionally qualified accounting staff it was decided not to fill these posts on a permanent basis but to make appointments on a temporary basis and carryout a revicw of accounting and budgeting fhnctions. The most recent attempts at recruitment by both direct advertising or through recruitment agencies have produced a very poor response. Applicants have not been qualified accountants. In once case an initial response of eight properly qualified persons was reduced to zero by the date of interviews.

3.2In January 2000 4 accountants were appointed on a temporary basis for 6 months. Their contracts expire in July 2000.

3.3A review of the accounting and budgeting function is currently underway. A report on the outcomc of the review will be submitted to Policy and Resources Comrnittce in due course. It is anticipated that the rcview will be wide ranging and will take a significant period of time to draw to a conclusion. Thereafter the proposals will require to be implemented, staff recruited and allowance made for bedding down of the new proposals. 3.4 Whilst the review is underway and its recommendations are being implemented there will be an ongoing requirement for accounting and budgeting services in terms of the completion and audit of the annual accounts, completion of returns to the Scottish Executive, budget monitoring and budget preparation. In order to achieve this it is essential that the temporary contracts of the 4 accountants are extended through to January 2001.

3.5In the accounting profession the demand for temporary staff and the Councils own geographical location requires a premium of 20% on to what would be regarded as normal costs to be paid in order to permanent stafE In addition it is necessary to provide staff with an accommodation dlowance. Arising from these additional costs it has been estimated that to extend the 4 contracts for a further period of 6 months will incur costs which exceed the budget provision by &46,313.00. This additional cost can be funded by virement of savings achieved in loan charges through debt rescheduling of &47,148referred to in the report on debt rescheduling at agenda item 6.

4. CONCLUSION

4.1This report identifies the need to extend the contracts o f 4 temporary accountants for a further period of 6 months. It highlights that additional costs of &46,313.00 will be incurred as a result of this. It recommends that savings achieved in loan charges through debt rescheduling are vired to meet this additional cost.

5. IMPLICATIONS

5.1Personnel Extension of temporary contracts.

Legal None

Financial Ensures ongoing delivery of essential financial and accounting tasks.

Equal opportunities None

Policy None

For further information please contact Rruce West, Head of Accounting, 0 1546 604220.

27 April 2000 Report/26aprbwtemporaryaccountantsP&R

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TEMPORARY ACCOUNTANTSReport 113 KB DownloadRead as text

At this meeting

Whole meeting
2MINUTESAgreed 3REVENUE BUDGET PREPARATION 2001/2002Decided 4RENEWAL AND REPAIRS FUND - SPEND TO SAVEApproved
5TEMPORARY ACCOUNTANTSThis decision
6ANNUAL TREASURY MANAGEMENT REPORTAgreed 7DEBT RESCHEDULINGNoted 8PROPERTY VALUATIONS 1999/2000Noted 9CORPORATE POLICY - SUPPLEMENTARY ESTIMATEApproved 10ESTABLISHMENT OF AN AUDIT COMMITTEEAgreed 11LOCAL TAX COLLECTION: PERFORMANCE AT 31 MARCH 2000Noted 12NON-DOMESTIC RATES BEST VALUE SERVICE REVIEWAgreed 13COUNCIL TAX COLLECTION: IMPROVEMENT INITIATIVESNoted 14CAPITAL PROGRAMME 1999/2000 - OUTTURN REPORTNoted 153 YEAR CAPITAL PROGRAMME - FEASIBILITY STUDIESApproved 16CORPORATE RESPONSE TO STEPHEN LAWRENCE INQUIRY (THE MacPHERSON REPORT)Noted 17INTRODUCTION OF 38 HOUR WORKING WEEK: OVERTIME AND BONUS CALCULATORAgreed 18ABSENCE MONITORING FIGURES - APRIL 1999 - MARCH 2000Agreed 19DISCIPLINARY PROCEDURESAgreed 20BEST VALUE APPROACHAgreed 21STRATEGIC PRIORITY: OUTTURNS AND TARGETSAgreed 22ENTITLEMENT OF FOOTWEAR AND CLOTHING GRANTAgreed 23INFORMATION SECURITY MANAGEMENTApproved 24SCOTTISH TOURIST BOARD MEMBERSHIPAgreed 25GLASGOW AIRPORT CONSULTATIVE DOCUMENT - LOCAL AUTHORITY REPRESENTATIONAgreed 26COSLA: URBAN AND RURAL AFFAIRS MEMBERS NETWORKAgreed 27THREE YEAR CAPITAL PLAN 2000/2003 - CCTV SCHEMES - CAMPBELTOWN, HELENSBURGH AND DUNOONAgreed 28GAELIC IN THE COMMUNITY SCHEMEAgreed 29BUS SERVICES SUB COMMITTEEAgreed 30CONTAMINATED LAND - A NEW STATUTORY DUTYAgreed 31RATES RELIEF FOR PHARMACIES AND TOURIST INFORMATION CENTRESAgreed 32LOCH LOMOND INTERIM COMMITTEE - CAPITAL PROGRAMME 2000/2001Agreed 33HOUSING MANAGEMENT SERVICE: STAFFINGAgreed 34CHILDREN'S SERVICE DEVELOPMENT FUND: STAFFINGAgreed 35FLOOD PREVENTION AND LAND DRAINAGE (SCOTLAND) ACT 1997Agreed 36PROPOSED DISPOSAL/LEASE OF GROUND AT BLAIRVADACH, SHANDONDecided 37PROPOSED SALE OF CARDROSS ASSEMSSMENT OF CENTRE - CITY OF GLASGOW COUNCILAgreed 40The Committee resolved in terms ofOn the agenda 38CARE PLAN FOR A QUADRIPLEGIC SERIVCE USERPrivate 39BUSINESS/EUROPEAN UNIT, ROTHESAYPrivate 40NORTH PIER, OBAN - DEVELOPMENT PROPOSALSPrivate 41LEASE OF ADDITIONAL OFFICE ACCOMMODATION 64A JOHN STREET, HELENSBURGHPrivate 42WINTER GARDEN VISITORS CENTRE LTD, ROTHESAYPrivate

Who was there

0 of 26 attended
AM
Councillor Allan MacaskillMember, expected
AM
Councillor Archie McCallumMember, expected
CC
Councillor Campbell CameronMember, expected
DW
Councillor David WebsterMember, expected
DC
Councillor Douglas CurrieMember, expected
DM
Councillor Dugie MacKinnonMember, expected
EM
Councillor Elspeth McTaggartMember, expected
JS
Councillor John StirlingMember, expected
MS
Councillor Moyra StewartMember, expected
PC
Councillor Paul ColeshillMember, expected
RB
Councillor Robin BanksMember, expected
RK
Councillor Ronald KinlochMember, expected

All 26 on the meeting page

More from Argyll and Bute Policy & Resources Committee

All decisions
MeetingDecisionOutcome
15 Feb 2001 Revenue budget 2001/2002Decision The motion was carried by 12 votes to 9 and accordingly the Committee agreed to recommend to the Council:- 1... Agreed Open
15 Feb 2001 Housing revenue budget 2001/2002: proposals for rent increaseDecision To recommend to the Council – 1. That the rents of Council houses be increase by an average of £1.75 per wee... Decided Open
31 Jan 2001 Revenue budget 2001/2002Decision To recommend:- 1. Approval of the draft Revenue Estimates for this Committee’s Services for 2001/2. 2. To no... Approved Open
21 Dec 2000 Service plansDecision 1. That Members offer any responses to the Chief Executive/respective Directors within 28 days. 2. To remit ... Decided Open
21 Dec 2000 Shaw awardDecision The Committee agreed to offer congratulations to the staff of Personnel Services on their achievement. (Refe... Agreed Open