Decision 1. To note the terms of the report. 2. To approve the deferred start and the replacement of Largnahunison Bridge on the B8024 Kilberry Road from October 2001 to February 2002 in order to accommodate the estimated cost of £200,000 for the works on the Gallanach Road within the available Capital Budget for 2001/2002. (Ref: Report by Director of Transportation & Property dated 25 July 2001, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Members are asked to note the terns of the report and to approve the deferred start on the replacement of Largnahunsion Bridge on the B8024 Kilberry Road from October 200 1 to February 2002, in order to accommodate the estimated cost of E200,OOO for the works on the Gallanach Road within the available Capital Budget for 2001/2002.
3. DETAIL
In accordance with the previous decision taken by the Committee, Edge Consultants have been appointed to carry out the final design and supervision of the works to stabilise the rock face adjacent to the C34 Gallanach Road.
a Similarly negotiations have taken place with firms of specialist contractors, capable of carrying out the works, and having regard to the unit rates quoted and their availability to commence operations, the contract was awarded to Rocklift Ltd of Barrhead, Glasgow, at an estimated cost of &140,000. This sum together with consultancy fees and the cost of necessary improvements to the diversionary route will bring the total cost of dealing with this emergency to approximately 5200,000.
Operations to stabilise the rockface commenced on site on 24 July and are scheduled to be substantially completed and the road reopened to traffic within a period of 4 weeks. It is further proposed that the excavated rock will be utilised to strengthen coastal protection measures on the C34 north of the site.
4. IMPLICATIONS
4.1Policy - None.
4.2Finance - It is proposed to finance the cost of the works, estimated at &200,000,by deferring a start on the replacement of Largnahunsion Bridge on the B8024 Qlbeny
C:\windows\Temporary Internet Files\OLKEl8S\ra1609.doc 1 of2 25 July 2001 12
Road. While the subsequent delay to this project is regretted a diversionary route is available which avoids the existing weak structure which is subject to a 7.5 tonne weight restnction.
4.3Personnel -None.
4.4Equal Opportunities - None.
4.5Legal - Discussions are taking place with Legal Services regarding negotiations for land entry to carry out the works and for the installation of rock trap fencing. Similarly, discussions are taking place with British Telecom regarding measures to protect the fibre optic cable which provides a telecommunications link to Mull and is located within the road verge adjacent to the site.
For further information please contact A Gow (01546 604657).
C:\windows\Temporary lntemet Files\OLKEl85\ral609.doc 2of2 25 July 2001
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.