WINTER MAINTENANCE - LEVEL OF SERVICE - WINTER 2001/2002

Noted Committee 1 paper

Strategic Policy Committee noted this item on Thursday 27 September 2001. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision 1. To note the terms of the report and in particular, the increased costs of providing winter maintenance. 2. To agree to the revisions to operational procedure as detailed in the report in order to provide savings to alleviate the increased costs. 3. To continue consideration of recommendation 2.3 to the next appropriate cycle of the Strategic Policy Committee. 4. To refer consideration of the route priorities to Area Committees for comment and for them to report back to the Strategic Policy Committee with their views. (Ref: Report by Director of Transportation & Property, dated 19 September 2001, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Recommendation

2.1That the Committee note the potentially increased costs of providing a winter maintenance service to the Council, following the loss of the Trunk Roads maintenance contract.

2.2That the Committee agree the revisions to operational procedures as detailed in the report in order to make savings which will alleviate the effect of the increased costs identified in Appendix 1.

2.3That, where following a mild winter there is an under-expenditure on winter maintenance, any surplus from Transportation returned to the general fund, should be earmarked for winter maintenance in future years. e 3. BACKGROUND

3.1Members will be aware of the decision by the Scottish Executive to award the Trunk Roads Maintenance Contract to BEAR Scotland, with the result that winter maintenance services on the Trunk Road Network will be the responsibility of that company.

These services were previously carried out by the Council under an agency agreement with the Scottish Executive.

The effect of this change will be that the Council’s own gritting operations will no longer be integrated with the trunk road operations. A degree of duplicated road mileage travelled will consequently ensue as a result, and the allocation of a proportion of the fixed costs to the Scottish Executive will no longer be possible. The potential impact of this change will be to increase costs by some &209,000 (see Appendix 1).

Formerly, the winter maintenance operation was carried out by the division of the integrated network into 39 distinct routes. By removing the trunk road element, but

1 6 15.doc I:\Word\TypistsMGow\Report\ra 1of7 L9/09/01 54 retaining virtually the original level of geographical coverage on the Council network, this figure would be reduced to 32 routes.

In addition, the trunk roads represented a higher proportion of the overall cost than that reflected in route mileage alone owing to their strategic nature and the fact that key sections were at an altitude requiring more frequent treatment.

Procedures formerly in place also allowed certain pockets of the local road network to be treated at a higher level of priority than dictated by the Council’s Winter Maintenance Strategy, on account of the integrated operations e.g. some minor roads north of ConneI adjacent to the A828 were treated on the return to depot following the completion of trunk road operations. As the Council no longer has the option of integrating these routes, a review of route priorities has been undertaken, with a view to achieving the most efficient arrangement possible.

This exercise has inevitably resulted in an increase in unproductive mileage i.e. mileage travelled where no gritting operation is taking place, because of the need to treat these pockets of Council roads which are accessible only from the trunk road network e.g. the villages of Furnace, Connel, Port Appin, Bonawe, and South Shian. This will create an additional 60 dead miles overall on the amended routes. While the existing depots at 0 Dalmally and Appin are to be retained at present, there is a question over their longer term future. It is however recognised that their disposal may cause difficulties in dealing with routes such as the A819 Inveraray to Dalmally road.

There are a number of other costs which were previously met proportionately through the trunk roads agency agreement, but which will now have an impact upon Council’s budgets unless alternative measures are adopted.

These are:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WINTER MAINTENANCE: LEVEL OF SERVICE: WINTER 2001/2002Report 721 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 30 attended
AB
Alasdair BovairdCouncil Staff, expected
AM
Archie MortonCouncil Staff, expected
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
DW
Councillor David WebsterMember, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
RK
Councillor Ronald KinlochMember, expected
DF
Deirdre ForsythCouncil Staff, expected
ED
Elaine DochertyCouncil Staff, expected
SM
Stewart McGregorCouncil Staff, expected
GF
Councillor George FreemanMember, expected

All 30 on the meeting page

On this subject at Argyll and Bute

Search all
  1. WINTER MAINTENANCE - LEVEL OF SERVICE - WINTER 2001/2002This decision
  2. Winter maintenance community engagementNoted
  3. Winter maintenance policy review 2006Agreed
  4. Winter Maintenance Policy Review 2006Agreed
  5. Winter maintenance policy review 2006Decided
  6. Winter maintenance footway clearanceNoted

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies