Decision The Committee agreed to write to the director of Operational Services representative in the following terms:- The committee do not agree with the recommendations made to the Strategic Policy Committee on 24 th August 2006 The Committee do not agree with the prioritisation of roads as contained in the paper submitted to the Strategic Policy Committee, specifically the A886 Strachur to Colintraive Road being priority two. Ask that the Director of Operational Services investigate all possible sources of funding with a view to continuing the winter maintenance service which the Council have given in past years. (Reference: Report by the Director of Operational Services dated 16 th August 2006 – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1In order to comply with the Department for Transport ruling regards the status of pre-planned winter maintenance operations as “non-emergency”, it is necessary to revise the timings and extent of treatments outwith normal working hours. To offset this, adjustments in working practices and measures to alleviate the need for repeat treatments, have been developed. The current Policy Document requires adjustment to include these measures. Clearer guidelines, as to the extent of treatment which the travelling public and other interested parties can expect, have been written in order to protect the Council Officers directly involved in the management of the Winter Maintenance service from the potential for prosecution and enhance the Council’s ability to defend insurance claims.
Recommendations
2.1That the Committee approves the revisions as indicated to allow implementation of the revised policy prior to 1 November 2006.
2.2That the Committee takes note of the efforts of Operational Services to increase the overall efficiency of the winter maintenance service by the introduction of new equipment, facilities and technologies whilst still maintaining the road and footway network in as safe and reasonable a condition, as is considered practicable.
Background
3.1Regulation 2 of Drivers Hours (Goods Vehicles) (Exemptions) Regulations 1986 states that, under domestic rules, a driver may drive for a maximum of 10 hours within an 11 hour working day. This can only be exceeded in “cases of emergency” which are defined thus, in the context of Local Authority winter maintenance:- (a) Events which cause or are likely to cause (i) Danger to life or health of individuals (ii) Serious disruption to public services (iii) Serious interruption to use of roads (b) Events likely to cause serious damage to property, if not dealt with.
3.2However, there is a ruling from the Department for Transport ( DfT) on what constitutes an emergency. Clarification of the above from the Fleet Transport Association (FTA) including extracts from the DfT letter is available on request. Page 158
3.2The DfT letter indicates that “emergencies” do not include any events that could reasonably be foreseen, two hours in advance. This includes all pre-planned winter treatments which are instigated in response to weather forecast information. Effectively, the Council cannot instruct a driver to carry out an early morning treatment in response to a weather forecast from the previous evening, predicting hazards in the morning, then ask the same operative to work a normal shift and then ask them to carryout a further treatment that same evening, in response to the updated mid-day forecast. This has been a common practice until now.
3.3At some point in the above sequence of events the operative has to be relieved of all working duties for a minimum rest period of 7 hours. This will clearly be impracticable in the case where they may not stand-down one evening until near to mid-night and then have to mobilise again for another planned action at 6am the following morning.
3.4Whilst these Regulations have been in place for some time, the DfT is now starting to look closely at roads operating company practices. Whilst this has been confined to England to date, there is at present a ruling pending against BEAR Scotland Ltd relating to extended hours worked during winter 2004-2005. It should be noted that for the following winter, this company employed a revised system of overnight shifts by a separate crew, who took no part in the day time routine maintenance operations. The new trunk roads operating company Scotland TranServ Ltd are employing a similar policy for the coming winter. It should be noted however, that with the exception of two routes, all other resources are external to the Argyll area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.