Resolved
Decision Approved the progress made with the Annual Audit Plan for 2001/2002. (Ref: Report by Internal Audit Manager dated 8 October 2001, submitted)
Audit Committee approved this item on Thursday 8 November 2001. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Approved the progress made with the Annual Audit Plan for 2001/2002. (Ref: Report by Internal Audit Manager dated 8 October 2001, submitted)
3 1 The report contained in Appendix 1 lists the audits scheduled for the financial year 2001 -2002 and details the progress that has been achieved to date with the annual audit plan The report is set out under the following headings, planned audits with audit reference, the name of the audit, percentage complete, planned, actual and remaining audit days The last column headed comment gives a commentary for each audit.
3.2In the 1st quarter of the financial year the Focus for Internal Audit was external audit work. This continued into the 2ndquarter when we were requested to cover additional work for external audit. Assistance was therefore given in respect of Performance Indicators.
3.3Internal Audit in the 2"dquarter carried out Follow up Reviews and this lead in some cases to additional work and additional reporting. Internal Audit was also involved in a number of Special Investigations (See Appendix 1).
3.4As indicated in the previous report to members Core Financial Systems and Departmental Audits were covered in the 2"dquarter. It is envisaged that for the remainder of the financial year Internat Audit effort will be predominately focused on Core Financial Systems and Departmental Audits. An indication of when audits will be covered is given in the comment column of Appendix 1
4. SUMMARY OF 2nd QUARTER AUDIT ACTWITIES FOR 2001 - XI02
4.1Through the Znd quarter Internal Audit staff numbers remained constant at 4. In addition 3 contract auditors were employed in the 2ndquarter to help deliver the audit plan. This gave the section a substantial boost in professional input. Their employment was initially for a period of two months however, 2 contract auditors were retained for the month of September,
42 As can be seen from the report set out in Appendix 1, the remaining audit day requirement for quarter's-3 & 4 totals 569. An analysis of available audit staff days 226
for quarter’s 3 & 4 revealed that after consideration for maternity leave for a member of staff, deductions for holidays and an estimate for sickness, available staff days totalled approximately 443 for quarter’s 3 & 4. This leaves a shortfall of 126 audit days. Two contract auditors have therefore been retained for the 3d quarter.
4.3A total of 212 days was set aside within the annual plan for external audit work. Of the 212 days a total of 92 days were alloted to Stock and Year End work, 40 days to Housing Benefit Grant Claim work and 80 days to Performance Indicators. In the Znd quarter a further 20 days were incurred on stock in reviewing stock sheet and shelve accuracy across Council stores. This brought the total stock audit days used to 57 leaving a balance of 3 5 days for the second half of the year. Assistance on Performance Indicator work was provided to external audit out with the programme of 80 days. This resulted in an extra 56 days to that originally planned.
4.4With regard to Housing Benefit Grant Claim, audit work is now scheduled to begin in November 2001when the Housing & Social Work Department are promised to have finalised the claim. External audit has already carried out some systems testing of the grant claim and therefore this should reduce our level of audit work to less than the 40 audit days planned.
4.5Of the 5 Core Financial Systems Audits scheduled for review this financial year, 2 have been carried out. In both audits actual days expended compared favourably to p h . The remaining 3 audits are scheduled for the 4’” quarter. (See Appendix 1).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PROGRESS REPORT ON INTERNAL AUDIT PLAN 2001/2002Report | 195 KB | DownloadRead as text |
Follow Audit Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2017 | Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... | Noted | Open |
| 24 Mar 2017 | Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... | Noted | Open |
| 24 Mar 2017 | External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... | Noted | Open |
| 24 Mar 2017 | Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... | Agreed | Open |
| 24 Mar 2017 | External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.