Resolved
Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March 2017, submitted)
Audit Committee noted this item on Friday 24 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March 2017, submitted)
1.1Internal Audit document the progress made by departmental management in implementing the recommendations made by both External Audit and Internal Audit. This report and attached appendices are the results from a review performed by Internal Audit for recommendations due to be implemented by 31 January 2017.
1.2The process requires departmental Executive Directors assigning a 3rd tier officer to act as the sole contact for the follow up of both external and internal recommendations. The contact role involves updating both the Executive Directors and Internal Audit on progress with agreed audit recommendation implementation.
1.3Appendix 1 is a statistical summary of all agreed recommendations arising from National, External and Internal Audit reports by department. Detailed is the number of recommendations due as at 31 January 2017, the number implemented, the number of agreed future recommendations and their status, e.g. on course etc.
1.4Appendix 2 provides a summary as at 31 January 2017, of all outstanding recommendations from National, External and Internal Audit reports by department and service. Detailed is the report name along with the weakness identified, agreed management action, revised date, any previous implementation dates reported to the Audit Committee management comment and Pyramid status
2.1The audit committee note the content of this report.
3. CONCLUSION
3.1Of the recommendations due for completion by 31 January 2017, 17 have been completed. Internal Audit is satisfied with the status of the remaining 6 recommendations being delayed but rescheduled. Good progress is being made on the recommendations due after 31 January 2017 with 7 completed early and the remaining 22 showing on course. Further programmed testing of post follow-up actions will be undertaken via the continuous monitoring programme. 4. IMPLICATIONS
4.1Policy: None
4.2Financial: None
4.3Legal: None
4.4HR: None
4.5Equalities: None
4.6Risk: Failure to implement agreed actions leads to financial, physical and reputational loss and adversely impacts organisational objectives.
4.7Customer Service: None
Kevin Anderson Chief Internal Auditor 24 March 2017
For further information please contact: Kevin Anderson, Chief Internal Auditor (01369 708505)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SERVICE SUMMARIESAppendix 1 | 250 KB | Download |
PDF |
All Outstanding RecommendationsAppendix 2 | 201 KB | Download |
PDF |
EXTERNAL & INTERNAL AUDIT REPORT FOLLOW-UP 2016: 2017Report | 78 KB | DownloadRead as text |
Follow Audit Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2017 | Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... | Noted | Open |
| 24 Mar 2017 | Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... | Noted | Open |
| 24 Mar 2017 | Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... | Agreed | Open |
| 24 Mar 2017 | External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... | Noted | Open |
| 24 Mar 2017 | Strategic risk assurance mappingDecision The Committee noted; a) the report: and b) the Risk Assurance Map. (Reference: Report by Grant Thornton date... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.