Decision Agreed to:- 1. Note the contents of the report and summary of the outline business case. 2. Lodge the Outline Business Case with the Scottish Executive as the core bid for revenue support for a school building PPP project noting the additional funding requirement from the Council as contained in the Board’s report. 3. Lodge a variant bid to include work to the school hostels. 4. Identify the resources necessary, estimated to be in the region of £1m. in the next financial year, for internal secondments and external advisers to further develop the PPP approach and the NPDO model if the application was successful. 5. Agreed to continue the Project Management Board at this time. (Ref: Report by Project Management Board dated December 2001, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1As part of the School Improvement Agenda, the Scottish Executive has invited councils to make applications for revenue support for school building Public Private Partnership (PPP) projects. The Executive has announced that the level of funding available to support educahon PPP projects is E500 million. Applications for the first tranche, in the form of an Outline Business Case (OBC), must be lodged with the Scottish Executive by 14 December 2001. Members will be aware that, in association with Partnerships UK (PUK), a project team has been developing proposals for Argyll and Bute in the form of an Outline Business Case (OBC) under the direction of the Project Management Board (membership details Appendix 1). The OBC contains commercially sensitive information and is not generally available. However, a copy of this OBC is available for inspection by members in the Project Office in Dunoon, and any member wishing their own copy should contact the project office and arrangements will be made to provide this.
Recommendations
It is recommended that the Council:
note the contents of this report and summary of the Outline Business Case; agree to lodge the Outline Business Case with the Scottish Executive as the core bid for revenue support for a school building PPP project noting the additional funding requirement from the Council contained in the paper. agree to lodge a variant bid which includes work to the school hostels. In addition; agree to identify the resources necessary, estimated to be in the region of &Imillion in the next financial year, for internal secondments and external advisers to further develop the PPP approach and the NPDO model if the application is successful.
Background
3.1An announcement of further PPP project funding for schools was widely expected and in anticipation of this, the Council endorsed (September 2000, April 2001, August 2001) papers recommending the establishment of a PPP schools project team and the development of the NPDO (non-profit distributing organisation) model. These decisions have enabled much work to be undertaken to ensure that this Council is able to lodge an OBC with the Scottish Executive for consideration in the first tranche of funding. The results of applications submitted in December 200 1 will be made known by the end of April 2002. . 3.2 The structure of the OBC had been established in advance by the Scottish Executive and councils have been provided with guidance on its completion. The OBC contains commercially sensitive information and is not generally available. The OBC has been prepared by the Head of Service - Capital Funding Project, and is based on discussions with the Council’s co-sponsors, Partnerships UK, as well as professional advice received from
c:\sharedfoldcr\mg\councilpaper.doc 1 other specialist external contractors and advisers. (contractor/adviser details are in Appendix 1)
3.3An executive summary of the OBC is attached as Appendix 2. It contains the essential elements of the OBC - its aim, approach, intention and methodology but without any of the commercially sensitive detail.
3.4Within a PPP agreement a consortium will contract to design, build, finance and operate (DBFO) an asset-based service. The public sector client pays a fee, an annual service charge, over the life of the contract to the consortium. This fee, in part, is contingent upon the quality of services provided meeting pre-specified and agreed standards.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.