Decision The Environment, Development and Infrastructure Committee – 1. noted the process for applying to the Islands Programme and Carbon Neutral Islands Capital Fund and the 22 July 2025 deadline for applications; 2. approved the recommended Island Programme projects detailed in paragraph 4.10 of the report which would form the basis of funding bids to the Scottish Government; 3. approved the submission of any of the potential CNI Capital Fund Projects listed at paragraph 4.15 of the report, subject to the project lead determining that this is still a project that should be progressed; 4. noted the process for applying to the Regeneration Capital Grant Fund and the 27 June 2025 stage one deadline; 5. approved the submission of any of the recommended RCGF projects listed at paragraph 4.22 of the report that would form the Expressions of Interest from Argyll and Bute Council to the Regeneration Capital Grant Fund for 2026/27; 6. agreed to delegate authority to the Executive Director with responsibility for Development and Economic Growth to approve the funding applications prior to submission to the Scottish Government; and 7. noted that the Transformational Projects and Regeneration Team would be responsible for managing expenditure and ensuring compliance with grant funding conditions for successful projects. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 4 June 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The Scottish Government has announced that Islands Programme funding of £5.3m would be available for the 2025/26 financial year to fund capital projects on inhabited Scottish islands. A further £1.4m is available to support the Carbon Neutral Islands (CNI) in their progression towards net zero. In addition, a call for stage one Expressions of Interest for Regeneration Capital Grant Fund (RCGF) applications for projects delivering in the 2026/27 financial year has also recently been issued. This paper outlines the funds, the respective requirements for applications to each fund and progress made towards identifying projects for submission. All three funds have made a significant contribution to the delivery of capital projects across Argyll and Bute over previous years. 1.2 Members are asked to note that these are all highly competitive funds and based on previous years it is considered likely that budgets will be oversubscribed. Once applications are submitted, the Transformation Projects and Regeneration Team will continue to have a role in ensuring that we fulfil the grant conditions including monitoring and reporting requirements. Project Officers within lead organisations will be responsible for managing the delivery of successful projects and ensuring all funding is drawn down in line with the criteria for the programme.
Recommendations
It is recommended that the Environment, Development and Infrastructure Committee:-
i). Note the process for applying to the Islands Programme and Carbon Neutral Islands Capital Fund and the 22 July 2025 deadline for applications. ii). Approve the recommended Island Programme projects detailed in paragraph 4.10 that will form the basis of funding bids to the Scottish Government.
iii). Approve the submission of any of the potential CNI Capital Fund Projects listed at paragraph 4.15, subject to the project lead determining that this is still a project that should be progressed.
iv). Note the process for applying to the Regeneration Capital Grant Fund and the 27 June 2025 stage one deadline.
v). Approve the submission of any of the recommended RCGF projects listed at paragraph 4.22 that will form the Expressions of Interest from Argyll and Bute Council to the Regeneration Capital Grant Fund for 2026/27.
vi). Agree to delegate authority to the Executive Director with responsibility for Development and Economic Growth to approve the funding applications prior to submission to the Scottish Government.
vii). Note that the Transformational Projects and Regeneration Team will be responsible for managing expenditure and ensuring compliance with grant funding conditions for successful projects. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE DEVELOPMENT AND ECONOMIC GROWTH 19 JUNE 2025
SCOTTISH GOVERNMENT FUNDING - ISLANDS PROGRAMME, CARBON NEUTRAL ISLANDS CAPITAL FUND AND REGENERATION CAPITAL GRANT FUND
2.0INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.