Item4
Resolved
Decision Noted: 1. The arrangements that had been made to alter the programme in view of the anticipated areas of slippage and variation. 2. The projected outturn in terms of expenditure and the number of properties treated, as outlined within Appendix A of the report by the Director of Housing & Social Work. 3. The general progress that had been made on projects under the principal expenditure heads during the first 4 years of the Council’s operation, as outlined in Appendix B of the report. (Ref: Report by Director of Housing & Social Work dated 14 January 2002, submitted) *