Decision To note the projects listed in Section 4A which have been discontinued due to lack of support. To authorise the continuation of the services listed in Section 4B. To authorise the introduction of the new services/projects listed in Section 4C. That in the event of continuing poor performance on any of the grant supported services, to authorise the Director of Transportation & Property Services to discontinue such services and bring a further report back to the Strategic Policy Committee to consider the introduction of selected services from Section 4D within the available budget. To note the projects listed in Section 4E for which no funding is available at present. (Ref: Report by Director of Transportation & Property Services dated 9 April 2002, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The purpose of this paper is to seek Committee’s approval for the allocation of the expenditure of Rural Transport Grant for the financial year 2002/03. The affected Area Committees were requested to submit suggestions for new and experimental services to be supported by Rural Transport Grant during the forthcoming financial year and these are considered in addition to the introduction of services successfully supported in previous years.
Recommendations
That the Committee:-
(i) note those projects listed in Section 4A which have been discontinued due to a lack of support.
(ii) authorise the continuation of the services listed in section 4B.
(iii) authorise the introduction of the new services and projects listed in section 4C.
(iv) in the event of continuing poor performance on any of the grant supported services, authorise the Director, Transportation and Property to discontinue such services and bring a further report to the Strategic Policy Committee to consider the introduction of selected services from section 4D within the available budget.
(v) note the projects listed in section 4E, for which no funding is available at present.
Background
For the last four years the Scottish Executive has provided the Council with additional funding for the promotion of rural public transport services within the authority’s area. The settlement figure for 2002/2003 is £377,000 of which the Scottish Executive has allocated £59,000 to Strathclyde Passenger Transport leaving a balance of £318,000 for services in the remainder of Argyll and Bute. Just over £250,000 of this sum is recommended to be used to continue support for previously authorised projects (section A). This includes a sum of £120,000 used over each of the last four years to support existing services, which would otherwise have been discontinued by the Council in 1998.
F:\moderngov\data\published\Intranet\C00000188\M00000683\AI00002631\RuralTransport2002030.doc 1 of 14 26 April, 2002 £68,700 remains, therefore, to promote new projects. The recommended new services are summarised in section B.
In order to gauge the performance of the services provided under the auspices of the Rural Transport Grant, the objective criteria contained in the Council’s Public Transport Guidelines have been applied and appropriate comment is included within the text of the appendix where applicable. A number of services in section B do not as yet meet the criteria but are achieving growth in terms of patronage, in line with the objectives of the introduction of the Rural Transport Grant and it is proposed that these services continue to be supported. A number of others however have been performing poorly, and have already been withdrawn. It is proposed that, as in previous years, those experimental services not achieving growth be discontinued and replaced by others of an experimental nature.
4. RURAL TRANSPORT GRANT EXPENDITURE 2002/2003.
(For further details of the undernoted services, please refer to the appendix accompanying this report.)
Section A. Information on services which have been discontinued during financial year 2001/2002 due to lack of support.
Appin and Oban from 19 February 2001 for six months Craighouse (Jura) and Bowmore from 25 January 2001 until 31 March 2002 Inveraray and Lochgilphead from 9 April 2001 until 30 September 2001 Jura Ferry from 21 October 2001 until 28 March 2002 Oban and Bonawe from 26 October 1998 until 14 October 2001
Section B. Services and projects in operation or approved previously which are recommended to be continued.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.