Item7
Resolved
Decision That a single refuse collection route within each area is transferred to full wheeled bin operation from 1 June 2002, as outlined in Section 3.4 of the submitted report, followed by a continuing programme of introduction until all routes are completed. That during the introductory phase of all individual routes, the price of a standard wheeled bin be reduced to a cost price of £18 plus VAT. (Ref: Report by Director of Development & Environment Services dated 18 April 2002, submitted)
Word for word from the decision Argyll and Bute published for this meeting.
Source: www.argyll-bute.gov.uk