Helensburgh & Lomond Area Committee noted this item on Tuesday 1 October 2002. Below is the council's own wording, with the papers it was decided on.

Item6c

Resolved

Decision (i) To note the footway upgrades already completed. (ii) To approve the locations listed for footway upgrades under Phase 5 of the programme. (iii) Agreed to add parking bays to Victoria Road. (iv) Agreed that future programmes should be headed Helensburgh and Lomond Footways. (Reference: Report by Principal Engineer dated 18 September 2002).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh & Lomond Area Committee

Summary

1.1The purpose of this report is to update Members on the locations of the footway upgrades already completed under Phases 1 to 4 and seek approval for the sections to be upgraded under Phase 5 during the 2002/03 and 2003/04 financial years.

Recommendation

2.1The Committee is asked to approve the locations listed for footway upgrades under Phase 5 of the programme.

Background

General

3.1The aim of the programme of footway upgrading in Helensburgh is to provide a network of surfaced footways in and around the town centre with links to outlying housing estates.

Funding

3.2Since Phase 1 in 1997, £400,000 has been spent on four contracts to upgrade Helensburgh footways. £100,000 has been allocated in the Capital Budget for both the 2002/03 and 2003/04 financial years. There is also funding of £35,000 available from the Cycling, Walking and Safer Streets budget. It has been agreed, on the grounds of economy, that one contract valued at £235,000 will be issued for the remaining programme, with the works running over the end of the financial year.

Works Completed (see attached sheet)

3.3Phase 1 (1997)

This phase was designed to provide an East-West link between the town centre and the outlying areas.

3.4Phase 2 (1998)

This phase was designed to provide North-South links from the outlying housing estates into the town centre. 3.5 Phase 3 (2000)

This phase was designed to fill in as many short ‘missing links’ in the surfaced footway routes around the town centre.

3.6Phase 4 (2001)

This phase upgraded footways in the vicinity of schools and the cemetery plus completing further missing links in the network.

Works Proposed (see attached sheet)

3.7Phase 5 (2002 / 03)

This year the works are designed to complete as many North-South and East-West links, partially completed under previous phases, together with a number of short un-surfaced sections around the town centre.

4. IMPLICATIONS

4.1Policy – None

4.2Financial – Monies allocated in the Capital Budget.

4.3Personnel – None

4.4Equal Opportunities – None

4.5Legal - None

For further information, please contact Craig Moir, Design Services, Helensburgh (01436 658850) HELENSBURGH FOOTWAYS – UPGRADE PROGRAMME

List of Completed and Proposed Works

Phase 1 (1997) To provide East-West links to Town Centre.

Street From To Side of Street

West King Street Glasgow Street Coulport Place South Granville Street Adelaide Street Henry Bell Street South Henry Bell Street Granville Street Old Luss Road North

West Montrose Street Sinclair Street John Street South (Revenue Funding)

Phase 2 (1998) To provide North-South links to Town Centre.

Street From To Side of Street

West King Street William Street Glasgow Street South (Postponed Phase 1) Charlotte Street Argyle Street East Abercromby Street East East Abercromby Street East Charlotte Street Railway Bridge South

West Montrose Street John Street Glasgow Street South (Revenue Funding)

Phase 3 (2000) To construct ‘missing links’ around the Town Centre.

Street From To Side of Street

West Princes Street William Street Glasgow Street South

West Princes Street At Bonar Law Avenue South

Easterhill Road Abercromby Street Bain Crescent East

East Princes Street Hanover Street Glenfinlas Street South

East Princes Street George Street Lomond Street South

East Princes Street At No. 91 North

West Argyle Street Sinclair Street 7 West Argyle Street South

A814 Rhu Road Lower Dalmore Crescent Rhu Road Higher North

West Montrose Street Glasgow Street Suffolk Street South (Revenue Funding) Phase 4 (2001) To improve footways near schools, upgrade the footway to the cemetery, plus some ‘missing links’ around the town centre.

Street From To Side of Street

Grant Street East boundary of West Hermitage Primary School

East Montrose Street Frontage of Parklands North School

Old Luss Road East King Street Cemetery West

East Abercromby Street Golfhill Drive Sannox Place East

Henry Bell Street East Clyde Street East Princes Street West

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Helensburgh Footways: Upgrading ProgrammeReport 78 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
ET
Councillor Eric ThompsonMember, expected
JS
Councillor John StirlingMember, expected
MS
Councillor Moyra StewartMember, expected
PC
Councillor Paul ColeshillMember, expected
RK
Councillor Ronald KinlochChair, expected
SW
Councillor Sheila WilsonMember, expected
SL
Councillor Stanley LatimerMember, expected
GF
Councillor George FreemanVice-Chair, expected
EM
Councillor Ellen MortonMember, expected
WP
Councillor William PetrieMember, expected

More from Argyll and Bute Helensburgh & Lomond Area Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... Noted Open
8 Sep 2026 Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... Noted Open
8 Sep 2026 Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... Noted Open
8 Sep 2026 Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... Noted Open
8 Sep 2026 Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies