AREA PLAN AND BUDGET

Noted Committee 3 papers

Mid Argyll, Kintyre & the Islands Area Committee noted this item on Wednesday 4 December 2002. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Decision A Revenue Budget It was noted that the only item which was unlikely to be spent was the £2000 improvement to Patchan Cemetery. It was agreed that alternative uses for this sum would be suggested by the Area Amenity Services Manager in consultation with the Local Member and approved by the Committee at their special meeting on 8 January 2003 immediately following the PAN 41 hearing in Tayvallich. The Area Roads manager will supply the list of roads projects dealt with from the revenue budget of £43,120. In regard to Campbeltown Airshow, it was agreed to transfer the grant to Campbeltown Common Good Fund to be retained in a ring fenced account so that assistance could be given to the Airshow in 2003 or 2004. If it is not required, the money will be reallocated to appropriate projects by the Area Committee. B Capital Budget It was noted that the footpath to Port Ellen Primary School would not go ahead and it was therefore agreed that the sum of £1,000 allocated to this project would now be spent on the formation of passing places on the Kintour to Ardtalla Road, Port Ellen. In regard to the Bike and Skateboard Park, it was agreed to obtain advice from the Director of Finance about the payment of the grant to Campbeltown Community Council and to report thereon to the said special meeting on 8 January 2003. In regard to the Junior Changing Facility, Campbeltown, it was noted that there were additional costs relating to piling. The Members expressed their full support for this project and agreed to consider whether to support this project with funding from the additional capital budget. C Additional Capital Budget of £15,0 93 It was agreed to allocate one third to each area viz (a) Mid Argyll, (b) Tarbert and Kintyre including Gigha and (c) Islay, Jura and Colonsay. The Members will bring forward proposals to the special meeting to be held on 8 January 2003. D Area Priorities It was agreed to advise the Chief Executive that the main priorities from the Area Plan taking one from each priority were as follows:- 1. Campbeltown and South Kintyre – Campbeltown Community Project 2. Partnership Projects - Argyll and Bute Sports Strategy which will lend weight to Mid Argyll Sports Trust. 3. Islay, Jura, Colonsay and Gigha - Bruichladdich Pier.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

MID ARGYLL, KINTYRE AND ISLAY Area Strategy and Action Plan

Mid Argyll, Kintyre and Islay Area Committee have agreed 2 geographical priority areas and 5 partnership priorities. Many of these involve Community Planning Partners.

The Committee have agreed that in regard to the geographical areas, service departments should target and prioritise these areas for any revenue funding which is not specifically allocated to service functions.

They further agreed that in regard to the 5 partnership areas, the first priority is to arrange meetings with other identified local partners to discuss action on each of these points.

The 2 geographical priority areas are

1. Campbeltown and South Kintyre

and

2. Islands of Islay, Jura, Colonsay and Gigha.

The specific priorities for these 2 areas are on Appendix (1) and Appendix (2). These include ongoing projects which have already been allocated funding.

Appendix (3) details partnership projects.

The Committee reviewed these priorities in September 2002 and will review them again in March 2003.

F:\moderngov\data\published\Intranet\C00000243\M00000947\AI00006059\AreaPlan04Dec020.doc 04December2002 Mid Argyll, Kintyre and Islay Action Plan Geographical Priority Campbeltown and South Kintyre

Projects When By Cost Partners Action whom * BNSF – Campbeltown 2002/2005 SW/ED £600,000 over 3 yrs Scottish Executive Project manager appointed * Community Facility – Campbeltown 2004 DES £2 million in Councils budget To be sought Planning Application £6 million total cost lodged * Community Schools Initiative 2001/2004 ED £600,000 over 3 yrs Scottish Executive Underway * South Kintyre Community Learning Plan 2001/2004 Com Ed £80,000 over 3 years S E/ABC/Local Rolling out now at Communities / Careers The Laggan and Partnership Tayinloan * Campbeltown/Ballycastle Ferry 2003 TAPS £5 million over 5 years Scottish Executive Specification out to (expected subsidy) Northern Ireland consultation Executive Scotland Office * Healthy Living Centre, Kintyre 2002/2007 ED/HSW £808,000 – commencing 1/1/03 ABC/Health Underway Trusts/Voluntary organisations * S.I.P. 2002/2004 HSW £200,000 ABC/Vol.Org/Health/ Ongoing AIE 1. Campbeltown Town Centre Traffic 2003/2006 TAPS £300,000 – over 3 years ABC Public consultation to Management public be arranged. consultation 2002/2003 2. Campbeltown Museum – 2004/2006 DES £2 million ABC/Historic Kevin Williams to Burnet Project – future exhibition space Scotland/HLF/other advise partners/CAKE 3. Town Centre Improvements 2002/2005 AIE/DES £4 million or less Historic Scotland Kevin Williams to depending on level of work undertaken HLF/ ABC/AIE advise 4. Campbeltown Airshow June 2003 CAKE/ £56,000 AIE/Sponsors/ABC Discussions (£20,000 from ABC) Campbeltown ongoing locally KIWG Common Good Fund 5. Improvements to Tayinloan ferry Longer term TAPS To be ascertained ABC/Scottish Investigate costs of terminal Executive/Calmac feasibility study * * funded projects

F:\moderngov\data\published\Intranet\C00000243\M00000947\AI00006059\AreaPlan04Dec020.doc 04December2002 Mid Argyll, Kintyre and Islay Action Plan Geographical Priority Islay, Jura, Colonsay & Gigha

Project When By whom Costs Partners Action

* BNSF – part of Atlantic Isles 2002 SW £600,000 over 3 yrs Scottish Executive Project Manager ABC appointed * 3 Islands Partnership, Islay, Jura and 2001/2002 CLS/IT £700,000 Scottish Executive All service points Colonsay ABC, AIE functioning Health Board * Port Askaig redevelopment 2002/2004 TPS £5 million EU/Scot Exec/ABC Out to tender

* Gigha Community Heritage Trust 2002 CLS £20,000 ABC Concluded but Start Up Costs ongoing support to community *. Colonsay Crofting Scheme 2002/2005 Crofters £6,000 CC/ABC/AIE/ Other Funding agreed Commissi partners on * Columba Centre, Islay 2002/03 Trust £2 million Trust/AIE/HIE Now open 1. Islay Hotel, Port Ellen 2002 AIE/DES To be ascertained AIE/Private Partners Meeting to take place ABC/Com.Scotland with owners

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AREA PLAN AND BUDGETReport 83 KB DownloadRead as text
PDF
Capital (04Dec02)Report 82 KB Download
PDF
Revenue (04Dec02)Report 80 KB Download

At this meeting

Whole meeting

Who was there

0 of 23 attended
AB
Councillor Alasdair BlairMember, expected
AM
Councillor Alastair McKinlayMember, expected
BR
Councillor Bruce RobertsonMember, expected
DM
Councillor Dugie MacKinnonMember, expected
DF
Deirdre ForsythSecretary, expected
JG
Jolan GergelyOfficer, expected
RM
Roddy McDowellOfficer, expected
HB
Hugh BlakeOfficer, expected
SB
Shona BrechinSecretary, expected
RC
Councillor Robin CurrieMember, expected
ID
Ian DownieOfficer, expected
IF
Ian FawcettOfficer, expected

All 23 on the meeting page

On this subject at Argyll and Bute

Search all
  1. AREA PLAN AND BUDGETThis decision
  2. Draft oban, lorn and the isles area committee workplanNoted
  3. Draft helensburgh and lomond area committee workplanNoted
  4. Draft mid argyll, kintyre and the islands area committee workplanNoted
  5. Bute and cowal area committee workplanNoted
  6. Appointment of vice-chair of the bute and cowal area community planning groupAgreed

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open