Decision (i) Agreed that a report be submitted to the next meeting of the Committee. (ii) Agreed that all relevant officers should be in attendance at the next Area Committee. (Reference: Report by Head of Amenity Services dated 17 February 2003).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The provision of a depot for council operations in the Helensburgh and Lomond area has been a need of the Council since its inception in 1996.
1.2The Council has now completed acquisition of approximately 4 acres of ground on Luss Road, Helensburgh which can be seen as a potential development site for a co-ordinated approach to depot facilities for the majority of council services operating in this area.
1.3This report advises members further on the development proposals for the site and indicates a programme of work necessary to take forward design and development needs.
Recommendations
2.1Members note that the works to put in place an access road across the site to the ground belonging to Helensburgh Golf Club is to be progressed in this financial year.
2.2Notwithstanding the lack of capital funding to secure future site development within current spending plans, that design staff start work on layout options for the site and revert to members of this committee at a future date to indicate possible designs and use of the site for approval by members.
3. DETAILS
3.1The site at Luss Road extending to approximately 4 acres is seen as providing a solution to different service needs of the Council. In particular the long term ability to have most heavy vehicle operations based at this location will allow a consolidation of separate facilities for Roads and Amenity Services functions and possibly the Building Services Direct Labour Organisation.
3.2The development costs of the site were subject of a bid for funding to the Council budget process for 2003/04, but due to competing demands, this bid was not successful. The provisional cost of works had been indicated at £1,000,000, spread over a three year period from the 2004/05 financial year onwards. These costs are in addition to the funding for the access road for the site, which is in the programme at a budgeted cost of £221,000.
3.3In spite of the bid being unsuccessful, there does remain a need to proceed with planning for development of the site, hence Recommendation 2.2. As well as provision for internal services, in looking at the site, the Council should also seek to consider joint approaches for development.
4. IMPLICATIONS
Policy: None
Financial: Substantial capital funding need, whether by traditional capital spending route, or otherwise
Personnel: None
Equal Opportunity: None
For further information contact: Andrew Law
Telephone 01546 604245
LIST OF BACKGROUND PAPERS: Reports on same subject to Helensburgh and Lomond Area Committee of 6 June 2003, 8 January 2002, 6 November 2001 and 2 October 2001, and to Strategic Policy Committee and Council on 27 June 2002
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.