Resolved
Decision To note the contents of the report. (Reference: Report by Project Director dated 17 February 2003).
Helensburgh & Lomond Area Committee noted this item on Tuesday 4 March 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the contents of the report. (Reference: Report by Project Director dated 17 February 2003).
1.1This report provides members of the area committee with an update on the progress of the Public Private Partnership (PPP)/Non-Profit Distributing Organisation (NPDO) schools project. The project notes that timescales have required to be moved to accommodate recent developments. The new timescales are noted together with a list of the project schools, the impact of recent unanimous Council decisions and an outline of the continuing communication and consultation strategy.
2.1The area committee is asked to note the contents of this report.
3. DETAIL
3.1In December 2002 the Council approved unanimously a report that recommended that a Revised Outline Business Case (OBC) be submitted to the Scottish Executive (SE) for its consideration and approval. A further paper to Council on 13 February 2003 noted that SE approval for the revised OBC had been delayed as a result of changes in accounting following the introduction of the Prudential Borrowing Regime. The effect of this change was such that it created potentially a significant increase in the affordability gap in the financial model. On 13 February 2003 the Council agreed unanimously to the recommendation that the Council reaffirm its intention to:
v develop a PPP project for schools; v maximise the revenue support on offer from SE; v bridge the affordability gap by a combination of the strategies noted in the paper.
3.2In agreeing these measures the Council restated that its strategic imperative remains the delivery of the much overdue and much needed improvements to the project schools at the scale and pace required. As a result of this unanimous decision, work has been undertaken to re-run the financial model and resubmit a final revised OBC to SE for consideration and approval. It is anticipated that approval for the OBC should not be unduly delayed.
3.3The revised timescale for the Project is noted below and the clear intention is to adhere to this timescale as closely as possible in order to avoid further delays and consequent contract time and cost overruns. Where possible, timetabling efficiencies will be utilised.
Timescale – Key Dates
13 February 2003 Council re-affirms its intention to proceed with project.
By end February Submit final revised OBC to SE.
F:\moderngov\data\published\Intranet\C00000244\M00001061\AI00008229\areacommittee10.doc 1 Early March Receive SE approval.
By end March Launch project notification in European Official Journal - the OJEC stage.
By end May Receive initial responses – issue Pre Qualification Questionnaire to bidders and invite to tender.
By end October Return of tenders.
March 2004 Identify Preferred Bidder.
December 2004 Financial close.
January 2005 Construction Phase begins.
December 2006 Target Completion Date for all project schools.
3.4The nominated schools in the project conform to both ministerial and Argyll and Bute priorities:
v Dealing with worst buildings first; v Securing value for money; v Support for 21st Century teaching; v Meeting wider community needs v Maintaining momentum and encouraging innovation; v Taking into account the number of pupils attending each building; v Adopting a geographic approach to grouping of schools to achieve where possible economies of scale; v Affording priority to secondary schools in order to address quickly, deficiencies in practical subjects.
3.5The schools identified for inclusion in the project are listed below. The OBC is predicated on all schools being rebuilt/refurbished on existing sites to a high quality standard. The standard of provision provided at day one must be maintained for the 30 year length of the contract and, as the contract is based on performance related payments, non-compliance by a contractor will result in non payment. Innovative solutions will be actively sought from potential contractors affecting all areas of provision.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PPP/NPDO Progress Report and UpdateReport | 98 KB | DownloadRead as text |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.