DEVELOPMENT CONTROL PERFORMANCE MONITORING AND SERVICE PLAN PROGRESS COUNCIL WIDE AND DECENTRALISED AREA TEAMS FOR 2002/2003
NotedCommittee2 papers
Mid Argyll, Kintyre & the Islands Area Committee noted this item on Wednesday 2 July 2003. Below is the council's own wording, with the papers it was decided on.
Decision 1. Members noted and endorsed the contents of the report. 2. Members agreed to a council wide target of 72% of all planning applications within two months for the period April 2003 to March 2004. This represents a 1% increase on last years target. 3. Members agreed to maintain the Scottish Executive’s target of deciding 90% of all householder applications within two months. 4. Members agreed that the targets set out in the report be adopted for each of the decentralised areas for the period April 20203 to March 2004. Bute and Cowal 77%, Helensburgh and Lomond 78%, Oban, Lorn and the Isles 65% and Mid Argyll, Kintyre and Islay 66% (Reference – Report by Director of Development and Environment Services dated 2 July 2003)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1This paper outlines my Departments Development Control performance with respect to processing applications as set against the performance target set by the four Area Committees in May 2002.
1.2In addition to reviewing the Council wide performance for April 2002 to March 2003, this report also identifies the performance and sets targets for each of the four decentralised areas for the period April 2003 to March 2004.
1.3This report also reviews and provides feedback on;
• Council wide performance set against the Scottish Executive’s targets for Councils as contained in Scottish Planning Policy 1: The Planning System (SPP1), dated November 2002. • Council Enforcement and monitoring activity. • Informal planning enquiries. • Planning appeals. • Fast tracked applications.
1.4Whilst my Department failed to reach the target of 71% (for all applications) for April 2002 to March 2003, my Department achieved 69%, which was a 2% improvement over the previous years performance. Notably, this is the highest level of performance achieved since re- organisation/decentralisation in 1996.
1.5With respect to householder applications, the Council again met its target of processing 90% of all householder applications within two months.
1.6As an appendix to this report the Council wide performance is included in the league table for Scotland. However, this period only covers the year April 2001 to March 2002, which is the most up to date statistic published by the Scottish Executive.
1.7In terms of all applications, the above appendix shows that Argyll and Bute’s performance is slightly above the Scottish average of 65% for the year 2001/2002.
Recommendation
2.1It is recommended that Members:
(a) Note and endorse the contents of the report; (b) Agree to a Council wide target of 72% of all planning applications within two months for the period April 2003 to March 2004. This represents a 1% increase on last years target. (c) Maintain the Scottish Executive’s target of deciding 90% of all householder applications within two months. (d) Agree that the targets set out below be adopted for each of the decentralised areas for the period April 2003 to March 2004. f:\moderngov\data\published\intranet\c00000243\m00001168\ai00009962\developmentcontrolperformancemonitoring0.doc • Bute and Cowal 77% • Helensburgh and Lomond 78% • Oban, Lorn and the Isles 65% • Mid Argyll, Kintyre and Islay 66%
Background
3.1As Members are aware the Scottish Executive Statistical returns are set against the targets contained in SPP1. This SPP deals with numerous aspects of Development Control and sets out the Scottish Executive’s expectations with respect to planning application performance.
3.2Within this SPP, the Scottish Executive not only reinforced that every Council should process 80% of all applications within two months but also identifies additional indicators, namely,
• 85% of all applications should be determined in three months; • 90% of householder applications should be determined within two months; • 95% of householder applications should be determined within three months; • 80% of major* applications should be determined within four months.
* Major is defined as applications for 10 or more dwellinghouses and business/industry applications which exceed 1000 square metres floorspace or if residential/business/industry applications have a site area of one hectare or more.
3.3Having due regard to the Scottish Executive’s expectations and the SPP, with particular regard to travel distances and logistics involved in providing a Development Control service in Argyll and Bute, Members, last year, agreed a target of 71% for 2002/2003.
3.4Table 1 – SPP1: Indicator 1.
Targets and Achievements since re-organisation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.