Decision Agreed to note the terms of the report subject to the amendment of “acceptance from” to “acceptance to” the strategic and locally significant list and “it is not vital to work up lobbying” to “it is now vital to” under the rubric “Future ERDF Programmes” (Ref: Report by Spokesperson dated 25 August 2003, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The primary aim of this project is to improve the berthing facilities at Bruichladdich.
The main issue at present is that Shell UK use single hulled tankers, which are about 70 metres in length. By the end of 2008, the Government will ban the use of this type of tanker in preference for double hulled vessels. These new tankers are about 90 metres in length. Failure to upgrade the facilities at Bruichladdich will have a major economic impact on the island. Fuel would have to be transported by road through Port Ellen and Port Askaig; and also the type of fuel used on the island would have to change from the current heated fuel oil to lighter non heated oils. The effect on industry on Islay and Jura would be to change their heating systems. Both the expense and the hassle would not be appreciated by the local businesses and communities. It is proposed to provide four berthing dolphins, four mooring dolphins and associated dredging work at an estimated cost of £2 million.
The Council has allocated £500,000 through the Capital Programme for the development work with grant funding identified through the Scottish Executive’s Freight Facility Grant (maximum of 50% of £2 million) and the European Regional Development Fund where the additional £500,000 is being sourced (European Funds are only available for the berthing work as the scheme has to be locally or strategically significant to qualify).
Concessionary Travel
“A Partnership for a Better Scotland” included the following commitments –
• To ensure that our transport system meets the needs of business, transport users and the environment by extending concessionary fare schemes on public transport, including a national free off-peak bus scheme for older people and people with disabilities.
• To ensure that our transport system meets the needs of business, transport users and the environment by assessing improved public transport concessions for people with disabilities.
• To ensure that our transport system meets the needs of business, transport users and the environment by progressively introducing a scheme of national bus, rail and ferry concessionary travel for young people, initially for all in full time education and training.
The Scottish Executive are currently working up proposals for delivery of these commitments and aim to identify the wide range of issues to be addressed through consultation and stakeholder buy-in. Strategic Transport Authority – A discussion paper will be launched by the Scottish Executive by the end of August and will require feedback on a range of options. The main aim is to ensure delivery of strategic, cross boundary projects and the preferred solution for the Highlands and Islands recognising the difference in the scale and nature of transport issues between the various regions.
Hitrans Air Network Proposal – Scottish Executive support in principle for the enhanced network has been confirmed. However, this is dependent on a thorough economic appraisal to confirm economic benefit. Hitrans officers and Scottish Executive staff will work together over the next few months on detailed assessments, and in parallel will devise the PSO bundles within the nextwork for discussion.
Highlands & Islands Special Transitional Programme – Transport infrastructure. The total available in this programme was £37.6 million of which £5.166 million was allocated to Locally Significant Projects and the balance of £32.434 million to Strategic Projects.
Funded from the Strategic list – Port Askaig - £1.663 million.
Funded from Locally Significant list – Argyll timber transport routes - £0.731 million.
Acceptance from Strategic list – Argyll Islands air services - £2.233 million.
Acceptance from Locally Significant list – Bruichladdich - £500,000; Campbeltown New Quay - £500,000.
There may be unallocated funds from both lists dependent on de-commitment of projects – reserve projects may be considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.