Resolved
Decision Noted the overall budgetary position and various matters identified in the submitted report. (Ref: Report by Head of Strategic Finance dated 28 August 2003, submitted)
Strategic Policy Committee noted this item on Thursday 4 September 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the overall budgetary position and various matters identified in the submitted report. (Ref: Report by Head of Strategic Finance dated 28 August 2003, submitted)
2.1To note the overall budgetary position and various matters identified in this report.
3. SUMMARY OF MAJOR BUDGETARY ISSUES
3.1YTD Actual V YTD Budget
The main budgetary issue facing the department at this point in the year and reflected in the June figures is that of maintenance to ferry vessels. There has already been significant spend to date on the Eilean Dhiura and virement has been proposed to take account of this increase. Significant expenditure required to the MV Belnahua arising from a recent inspection will be funded from capital.
3.2Projected Outturn Forecast
At this point there are no variances which are expected to affect the overall budget for this year.
3.3Objective/Subjective Summaries
Objective and Subjective Summaries are attached to this report and provide analysis at sub-service and expenditure category levels. It has been agreed that further information / explanation of variances of +/– 5% and above will be explained. The tables on the following page provide explanation of the variances meeting this criteria.
Objective Summary Variances • Roads (favourable £0.151m 5%) Work completed by DLO and not yet measured and paid. • Design Services (favourable £0.199m 92%) Income recovered earlier than phased in the budget. Timing difference only. • Traffic Management (favourable £0.080m 58%) Payment outstanding to DLO. • Public Transport (favourable £0.590m 51%) Payments by Education for school transport in advance of phasing. Timing difference only. • Contract Services (adverse £0.190m 395%)
Subjective Summary Variances • Supplies & Services (favourable £0.140m 48%) Mainly timing and coding difference on Ferries see below. • Transport (adverse £0.058m 28%) Mainly timing and coding difference on Ferries see above. • Income (favourable £0.754m 82%) Payments by Education for school transport in advance of phasing. Timing difference only. Income recovered on design services earlier than phased in the budget. Timing difference only.
3.4Detailed Variances A traffic light approach to monitoring is in place. This means detailed variance explanations are collected for all cost centres where the year to date variance is more than +/-£25,000 (red). Amber variances are those between +/-£5,000 and +/-£24,999. These are drawn to the attention of budget holders and managers with an instruction for investigation and strict monitoring to bring expenditure back in line with budget. Green variances are those between -£4,999 and +£4,999. The table on the next page summarises the position with red, amber and green variances.
Favourable Variances Adverse Variances
Value £m No Of Cost Value £m No Of Cost Centres Centres
Red 1.344 15 0.285 6 Variances Amber 0.166 16 0.167 16 Variances Green 0.047 55 0.182 182 Variances TOTAL 1.557 86 0.654 204 4. ACTION REQUIRED / ANTICIPATED FUTURE DEVELOPMENTS
4.1Supplementary Estimates
No supplementary estimates are required at this point
4.2Virements
Virement reports have been submitted to take account of emerging expenditure issues on ferry maintenance and also the situation on Dunoon Pier. The latter proposes to move £0.1m in budget from Bridge Maintenance to Piers and Harbours.
4.3Anticipated Pressure not yet reflected in Actuals
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Transportation & PropertyReport | 247 KB | DownloadRead as text |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.