Decision i) Agreed that paragraph 3.7 of the report was to be amended to read: “ Recognising the importance of this site as part of the Helensburgh West Waterfront, it is suggested that Members seek to put this project, as part of the wider waterfront development, at the top of their priority list for increased capital support from the Council, which in turn will allow greater gearing to be made of any external funding which might be available”. ii) Subject to the amendment detailed at (i) above, agreed the recommendations of the Strategic Director of operational Services, which required a referral to the Strategic Policy Committee recommending that £60,000 be added to the Council’s proposed expenditure in the capital programme for the financial year 2004/05 to take forward proposals for development of the Kidston Park Site, Helensburgh. (Reference: Report by Director of Operational Services dated 30 September 2003) The meeting was adjourned between 12 noon and 12.20pm for the Scheme of Local Liaison.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report is to advise Members of the Area Committee of issues around the potential development of the Kidston Park Public Convenience and surrounding area.
1.2The report also asks Members of the Local Area Committee to incorporate development of this site as part of their current priorities for development of the Helensburgh Waterfront.
Recommendation
2.1Members instruct staff from Operational Services and other parts of the Council to take forward proposals for development of the Kidston Park Site on a joint funding basis with capital commitment from the Council, input from Scottish Enterprise Dunbartonshire and external funding bodies who may commit grant support to the project.
2.2To facilitate 2.1, that the Helensburgh and Lomond Area Committee recommends to the Strategic Policy Committee in respect of the current proposed expenditure in the Council’s capital programme, that in the review of the programme this be increased by the addition of a further commitment of £60,000 for financial year 2004/05.
3. DETAIL
3.1The current public conveniences at Kidston Park form part of the overall public park and car parking area at that location.
3.2The conveniences over the years have been subject to vandalism, anti-social behaviour and dilapidation due to the inherently unsound building construction. Some cosmetic improvements have been carried out this year, resulting in a short term improvement.
F:\moderngov\data\published\Intranet\C00000244\M00001289\AI00011541\KidstonToilets0.doc 1 of 3 16 October 2003 3.3 Staff in Amenity Services have had a preliminary design for replacement of the current public convenience drawn up. This plan incorporates a café/snack bar and new public toilet with a budget cost of £254,000.
3.4In addition to that work there are concurrent proposals being drawn up to provide better parking, refurbishment of surrounding grounds and provision of an improved playground area. This work is, as yet, unpriced.
3.5The Council’s capital commitment to this project is currently £31,406, funding which had been seen at one time as potentially being utilised to transfer a portacabin unit from Luss Car Park. Given that the Luss Car Park unit has been in place now for over 5 years and is showing signs of disrepair, it is not recommended that this option be pursued.
3.6In order to maximise the potential for a joint approach in upgrading a facility on what is an important recreational site within Helensburgh and Lomond, approaches have been made to Scottish Enterprise Dunbartonshire and research is also currently underway into potential Heritage Lottery Funding and other possible sources of external funding. Feedback from Scottish Enterprise Dunbartonshire is that the project might possibly benefit from their support, including the potential for European Funding but that this would have to be seen as part of one of the Council’s main priorities for the Helensburgh and Lomond area.
3.7Recognising the importance of this site, it is suggested that Members seek to put this project at the top of their priority list for increased capital support from the Council, which in turn will allow greater gearing to be made of any external funding which might be available.
3.8Should extra capital funding become available and support from Scottish Enterprise Dunbartonshire seem realistic, then the Council could proceed to the next stage of development, i.e. finalising the current draft plan and proposals for improvements to the surrounding area and proceeding with a grant application process to match the Council’s available support.
4. CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.