Resolved
Decision Agreed that:- (1) The Council assumes responsibility for the Port Riddell Slipway and associated structures. (2) The structure be included in the Council’s public liability insurance cover. (3) The structural survey be carried out to assess and cost the remedial works which are currently required and the appropriate funding be provided from the Capital Programme to implement these works. (The survey had already been carried out). (4) Appropriate and additional revenue funding be provided in the budget process to enable Amenity Services, within Operational Services, to clean and maintain the Slipway. (Reference: Report by Director of Operational Services dated 11 November 2003, submitted).