Item5
Resolved
Decision Agreed that :- (1) The Queen’s Hall re-development proposals as detailed in the Consultant’s report be agreed in principle. (2) That the appropriate Officers of the Council make an immediate start on the processes associated with the project. (3) That the Council consider, within its budgeting process, including the costs of the project in the Capital Budget 2005/08. (4) That depending on the outcome of the foregoing, the Council consider at a later date giving a commitment to complete the project. (Reference: Report by Head of Democratic Services and Governance dated 11 November 2003 and recommendation of the Bute and Cowal Area Committee of 23 October 2003, submitted).
Word for word from the decision Argyll and Bute published for this meeting.
Source: www.argyll-bute.gov.uk