Decision 1. To note the strategy contained within the Roads Maintenance and Asset Management Plan. 2. That the Head of Roads completes presentations on the detail of the Plan to the Members of Area Committees by the end of May 2004 with a report coming back to this Committee as soon as possible thereafter. (Reference: Report by Head of Roads dated 29 March 2004, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1That members approve the strategy contained within the plan.
2.2That the Head of Roads completes presentations on the detail of the Plan to the Members of Area Committees by the end of May.
3. DETAIL
The Code of Practice for Maintenance Management "Delivering Best Value in Highway Maintenance" expects Road Authorities to implement a Highway Maintenance Plan which details the standards to which the authority will inspect and maintain its road network.
The Code highlights the importance of achieving "sustainability" in road maintenance and states :-
"The objective of "sustainability" is applied in this Code in the accepted sense of securing a balance of social, economic and environmental wellbeing that does not compromise the ability of future generations to meet their own needs. It is also applied in terms of financial and operational sustainability, ensuring that investment and operations resources are procured to avoid progressive deterioration of the asset. These are not incompatible, but together provide a significant challenge for the highway maintenance industry".
The plan is designed to allow members to be informed on the necessary budget to achieve this and to be aware of the implications on the Road Network if sufficient funds are not allocated.
The present budget is estimated to be underfunded by around 15% on routine and cyclic maintenance. The resurfacing, reconstruction and surface dressing programmes require around £3.5M to be spent over the next 5 years to clear the backlog and around £1.5M thereafter.
1 The plan allows standards to be set for all aspects of inspecting and maintaining the road network.
In terms of the proposed inspection regime this is somewhat less frequent than at present on the minor roads but more frequent on strategic routes. The current regime is for all routes to be inspected with a frequency of 3 months. The proposed inspection regime varies the inspection frequency dependant on the road hierarchy. Details of this are given in Table 4, Page 40.
The introduction of Find and Fix squads will also mean the many faults will be repaired as part of the inspection process thus improving the response times dramatically.
It is set within the context of an overall asset management regime the key principles of which are :-
Focus on lifecycle costing Management strategies for the long term Establishing and monitoring levels of service Managing risk of failure or loss of use Sustainable use of physical resources Continuous improvement
In line with the Code the plan will be set within an Integrated Network Management approach. The Code recommends that :-
"Highway maintenance policy needs to be developed integrally with the overall management of the network. Transport users, whatever their mode, do not distinguish between categories of road, or types of work, whether maintenance or improvement. It is irrelevant to them who is undertaking the work, whether local authority, contractor or utility. They expect the network to be managed and maintained holistically to provide consistent and appropriate levels of service and the ability to change modes as easily as possible.
Users also expect reasonable consistency of policy and standards on similar categories of highway irrespective of the responsibility for maintenance, which implies that all authorities both local and national should seek to deliver these expectations wherever possible.
Integrated network management also requires that all works on the highway network including maintenance, improvement, and new construction, are planned and managed integrally, also having regard to other influences on the network."
4. CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.