Resolved
Decision To note the position.
Policy Development Group noted this item on Wednesday 26 May 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the position.
REPORT TO HITRANS BOARD 16 APRIL 2004
BUDGET 2004/5
1. At the last HITRANS Board meeting on 13 February it was agreed that the budget for next financial year would be reviewed by the officers. The out turn in 2003/4 will be in the order of £250,000 and is detailed in Annex A. This will give rise to a deficit of about £37,000.
2. The annual contribution formula from partners was agreed at the December 2001 HITRANS Board, and is shown in Annex B. Over the past two financial years a total of £100,000 per annum has been invoiced to partners. At the last board meeting it was agreed to seek further contributions to cover the deficit for this financial year. Cameron Kemp will report separately on the 2003/4 out turn.
3. Activity during the coming financial year is likely to continue at the current level with the effort to establish the PSO on the Air Network, and to pursue the trunk road studies. Therefore a draft budget is set out below.
• Co-ordinator’s fees and expenses £55,000 • Admin support for co-ordinator/public transport officer £15,000 • Board Meetings £5,000 • Publicity (Intermedia fees and publications) £6,000 • Air Network Consultant fees £44,000 • Air Network other activity £5,000 • A82 Studies £35,000 • A96 studies £35,000 • Other Research £20,000 • HITRANS development (after S. Exec. White Paper) £20,000 • Lobbying and contributions to EU studies £10,000 Total £250,000
4. Based on this budget, and the formula in annex B, contributions for 2004/5 would be (2003/4 payments in brackets):
Scottish Executive £112,500 (45,000) Highland Council £30,500 (15,000) Highlands and Islands Enterprise £25,000 (10,000) Moray £20,000 (3,000) Argyll and Bute £18,125 (8,000) Comhairle nan Eilean Siar £14,750 (6,000) Orkney £14,375 (6,000) Shetland £14,375 (6,000) Arran and Cumbrae £375 (1,000) 5. Moray has agreed the new budget contribution, subject to all other partners agreeing their shares. Argyll and Bute, Orkney, and Shetland have indicated that they will have difficulty raising their contributions to the proposed level. Other partners will report at the meeting. Therefore it will not be possible to agree the budget at the April meeting.
6. I would recommend that an interim budget is agreed based on the draft above, and that funding contributions are revisited in August.
Howard Brindley April 2004 Annex A
Spending Out turn 2003/4 (to 9 February 2004)
Co-ordinator fees and expenses £41015.97 (This comprises fees for 10 months (£29800) and expenses which include £5000 for lobbying, transport awards, Nairn seminar, seaplane and islands transport studies)
Board Meetings £3258.91 (This comprises meals and room hire at about £900 per meeting)
Aviation and Travel Consultancy £44180.47 (This comprises work on the Air Network Proposal)
Steer Davies Gleave £44301.00 (This comprises work on the economic benefit appraisal of the Air Network)
Cranfield £3500.00 (This comprises work on PSO bundles)
Halcrow £27622.73 (This comprises work on the lifeline roads study)
Intermedia Services £10335.93 (This comprises work on publications, stationery, web site, and publicity)
Nairn Seminar £11700.64 (This is the cost of the seminar on Scotland’s Transport – 50% will be recovered from the Scottish Executive. A further £800 is included in the Co-ordinator’s expenses)
Islands’ Transport £9160.49 (This is the cost of contributing to the CPMR study. A further £1000 is included in the Co- ordinator’s expenses))
Annual Conference £2500.00 (This is our share of the Orkney conference)
Seaplane £1414.20 (This is our contribution to the Interreg Study. A further £1000 is included in the Co- ordinator’s expenses)
Westminster Lobby £1080.81 (This comprises the meeting with MPs on the Air Network. A further £1000 is included in the Co-ordinator’s expenses)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FUNDING OF HITRANSReport | 85 KB | DownloadRead as text |
Follow Policy Development Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Feb 2007 | Political management arrangementsDecision That the Director of Corporate Services finalise the draft report to reflect the discussion at the meeting a... | Decided | Open |
| 9 Feb 2007 | Consider information required to undertake remitDecision That the Policy Development Group recommend to the Strategic Policy Committee that they note: 1. the positiv... | Decided | Open |
| 31 Jan 2007 | Councillor remunerationDecision The Group noted the contents of the report and the representations made on behalf of the Council. (Ref: Repo... | Noted | Open |
| 31 Jan 2007 | Councillors' allowances and expenses regulations 2007Decision 1. The Group noted the report and the representations that had been made on behalf of the Council, including... | Noted | Open |
| 31 Jan 2007 | The scottish parliament: an awareness seminar for new councillorsDecision Agreed that the Director of Corporate Services accept the offer from The Scottish Parliament and that this b... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.