Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.
Decision The Committee endorsed the proposals of the securing of further external funding to offset additional costs by 1. Attempting to obtain the agreement of Scottish Water to their contributing towards the additional costs involved in connecting to the over stretched main sewer system and 2. Through the progressing of a grant application via ALIENERGY in order that funding can be provided for the Biomass Boiler installation following the demise of Torren Energy. (who were originally supplying boilers free of charge, the cost being recovered through the purchase of fuel/heat) (Reference – Report by Director of Community Services dated 2 June 2004)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1This report seeks to update members on the progress of the Campbeltown Community Project.
Recommendations
2.1Members are asked to endorse the proposals for the securing of further external funding to offset additional costs.
a) By attempting to obtain the agreement of Scottish Water to their contributing towards the additional costs involved in connecting to the over stretched main sewerage system. b) Through the progressing of a grant application via ALIENERGY in order that funding can be provided for the Biomass Boiler Installation following the demise of Torren Energy. (who were originally supplying boilers free of charge, the cost being recovered though the purchase of fuel/heat)
3. DETAIL
3.1See Appendix 1 – Project Managers Report
4. CONCLUSION
4.1The Campbeltown Community project has got off to a successful start on site. The contract is currently on track, with regard to timescale, and cost (of the original contract work). Steps are being taken to secure extra funding for additional costs incurred outwith the control of the design team.
5. IMPLICATIONS
5.1Policy: - Nil 5.2 Financial: - Nil (subject to the additional external funding being secured) 5.3 Legal: - Nil 5.4 Equal opportunities: - Nil 5.5 Personnel - Nil
Douglas Hendry Director of Community Services DATE 14/04/04
For further information contact: Allan Redpath on 01546 60 4296 APPENDIX 1
Project Managers Report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.