CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Strategic Policy Committee, Thursday 1 July 2004 at 10.30am

BUS ROUTE DEVELOPMENT GRANT SCHEME

Noted Committee 1 paper

Strategic Policy Committee noted this item on Thursday 1 July 2004. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

Decision 1. Noted the introduction of the Bus Route Development Grant Scheme as announced by the Scottish Executive. 2. Approved preparation and submission by 30 July 2004 of applications for the following 3 routes identified in conjunction with bus operators:- a) Oban and Dunbeg b) Oban and Fort William c) Oban and Perth (Reference: Report by Head of Transportation and Infrastructure dated 23 June 2004, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Summary

The purpose of this report is to seek members approval to submit three schemes identified in conjunction with bus operators for the first round of Bus Route Development Grant funding under section 70 of the Transport (Scotland) Act 2001.

Recommendations

It is recommended that members

(i) note the introduction of the Bus Route Development Grant Scheme as announced by the Scottish Executive.

(ii) approve preparation and submission by 30th July 2004 of applications for the following three routes identified in conjunction with bus operators:- (a) Oban and Dunbeg (b) Oban and Fort William (c) Oban and Perth

Background

(i) On Wednesday 21st April 2004 the Scottish Executive formally announced the launch of the Bus Route Development Grant scheme in accordance with their “Partnership for a Better Scotland” commitment. The overall purpose of the Grant is to improve access to public transport, encourage modal shift and reduce congestion. The grant is a section 70 transport grant under the terms of the Transport (Scotland) Act 2001.

(ii) The grant will provide financial support for up to three years to aid the development of new and existing registered local bus services that have the potential for growth. Bids for projects to start in 2004-05 must be identified in conjunction with bus operators and be set within the context of the Council’s Local Transport Strategy.

(iii) Projects for the initial round of funding must be able to demonstrate high potential for developing new and under-used registered bus services, achieving high levels of passenger growth, greater service frequency and quality and other significant benefits to passengers. Projects have to demonstrate the potential for routes to be fully commercially viable at the end of the proposed 3-year funding period. Particularly important for a rural area like Argyll and Bute where commercial viability is unlikely in the majority of cases, subsidised services and subsidised elements of services will also be considered for funding where growth can be demonstrated. However, the transport authority must agree to maintain the existing level of subsidy during the specified period of service or until commercial viability is achieved.

F:\moderngov\data\published\Intranet\C00000188\M00001735\AI00017432\BusDevGrantKickStartSPC0.doc 1 of 3 24 June, 2004 (iv) It is for local authorities to decide whether to bid, and if so, how many bids to make. Authorities are asked to bear in mind that it will only be possible to approve a limited number of bids, particularly in this first phase. It is suggested that if more than one bid is submitted they should be ranked according to priority. Bids co-ordinated on a regional basis involving voluntary regional partnerships, where they exist, will be favoured. Joint bids from more than one authority in respect of a cross boundary project will also be considered. It should be noted that if a local authority does not appear proactive and is slow to instigate bids then an operator could approach the local authority and require them to instigate a bid.

(v) Projects will need to demonstrate commitment from both the Council and the bus operator to achieving the stated aims and outputs of the project and to making it work over the grant period to achieve longer-term viability. The initial projects will also be required to participate in a research project.

(vi) Each application must be appraised in accordance with the principles set out in the Scottish Transport Appraisal Guidance (STAG). In particular it should be noted that projects will not succeed on the basis of social inclusion alone, factors such as congestion and modal shift will be of more importance. Operators and the Council have to act in partnership and submit a good business case to have a chance of their application succeeding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BUS ROUTE DEVELOPMENT GRANT SCHEMEReport 73 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 33 attended
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
DF
Deirdre ForsythCouncil Staff, expected
ED
Elaine DochertyCouncil Staff, expected
BB
Brian BarkerOfficer, expected
GF
Councillor George FreemanMember, expected
GH
George HarperCouncil Staff, expected
AH
Councillor Alison HayMember, expected
DH
Douglas HendryCouncil Staff, expected
AH
Amanda HuttonOfficer, expected

All 33 on the meeting page

On this subject at Argyll and Bute

Search all
  1. BUS ROUTE DEVELOPMENT GRANT SCHEMEThis decision
  2. Bus route development grant schemeNoted

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies