Decision Recommend to the Council:- 1. To approve inclusion of a scheme in the current Capital Programme of a project to upgrade the pier facilities at Rothesay to maximise the benefits to Bute from the introduction of the new Lower Clyde vessel, on the basis that there be no net cost in Loan Charges to the Council arising as a result of the scheme. 2. To approve an additional sum of £30,000 be included in the 2004/05 Capital Budget, out of the preliminary scheme cost of £3.0m for a preliminary design study and STAG appraisal (Scottish Transport Appraisal Guidance) to be undertaken to investigate the issues arising from the introduction of the new Lower Clyde Vessel and the benefits of the scheme. This cost to be incurred on the basis of no detriment to progress on other schemes in the Capital Programme and that the costs will be recouped from external funding sources and increased income, as described in Paragraph 3.9 of the report, should the scheme progress. 3. To approve the appointment of external Consultants to prepare the design elements of the projects as necessary, subject to the fees being recouped as part of the project funding package. (Reference: Report by Head of Transportation and Infrastructure dated 27 May 2004, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report sets out the implications on the Council of the proposed improvements to Caledonian MacBrayne ferry operations to Rothesay with the introduction of the new Lower Clyde Vessel in 2005.
Recommendations
2.1That the Committee recommends to the Council:
2.2That the Council approved inclusion of a scheme in the current Capital Programme of a project to upgrade the pier facilities at Rothesay to maximise the benefits to Bute from the introduction of the new Lower Clyde Vessels, on the basis that there be no net cost in Loan Charges to the Council arising as a result of the scheme.
2.3That the Council approves an additional sum of £30,000 be included in the 2004/05 capital budget, out of a total preliminary scheme cost of £3.0m, for a preliminary design study and STAG appraisal (Scottish Transport Appraisal Guidance) to be undertaken to investigate the issues arising from the introduction of a new lower Clyde vessel and the benefits of the scheme. This cost is to be incurred on the basis of no detriment to progress on other schemes in the Capital Programme and that the costs will be recouped from external funding sources and increased income, as described in Paragraph 3.9, should the scheme progress.
2.4That the Committee approve the appointment of external Consultants to prepare the design elements of the project as necessary, subject to the fees being recouped as part of the project funding package.
Background
3.1Caledonian MacBrayne Limited presented their proposals for the new Lower Clyde Vessel to run on the Rothesay-Wemyss Bay service at a meeting of the SSAC held in January 2004. This raised a number of issues that will impact on our shore-based facilities. The Company indicated it intended in the longer term to run two vessels on the route to replace the existing Streakers.
3.2The first new vessel has the capacity to accommodate 60 cars and 450 passengers in comparison to the present Streaker’s capacity of 36 cars and 381 passengers.
3.3The Scottish Executive have carried out a route appraisal for the service proposal that has identified that a roll on roll off facility should be provided at Rothesay in due
1 course, but not before Spring 2005, which is the present estimated delivery date for the new vessel.
3.4To maximise the benefit of provision of the new larger vessels required provision of a RoRo end loading linkspan as distinct from the present side loading facility, to reduce turnaround time and maximise the vehicles carrying capacity. At a meeting between officials from Caledonian MacBrayne, the Scottish Executive and the Council it was confirmed that provision had been made in the 1980’s redevelopment of Rothesay Pier to potentially serve a Hebridean Isles size vessel with end loading configuration.
3.5The new vessel has been designed to have both end and side loading capability for use during the interim period when there is no RoRo facility, but with reduced capacity in the side-loading mode.
3.6It is essential that the present mustering and disembarkation arrangements be reviewed, as they are incapable of dealing with the increased traffic volume carried by the new vessel. The intention is that the new vessel will have a turnaround period of 15 minutes.
3.7The new vessel’s passenger access arrangements from the quayside, which significantly differ from that of the present vessels, will have to be separately addressed by Caledonian MacBrayne in consultation with the Council, such that they meet the needs of the new vessel and all current vessels likely to serve the route.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.