Item3g
Resolved
It was agreed to allocate the available sum as follows: (a) Strengthening and resurfacing the C54 Lochbuie Road, Isle of Mull - £50,000; (b) Reshaping and resurfacing the worst section of the U16(O) Laurel Road, Oban - £20,000; and (c) New Passing Places on the U19 Connel – Barran Road - £15,382. Arising from this, it was agreed to undertake a review of the current list of strategic priorities for the Oban, Lorn & the Isles area. (Ref: Report dated 26 th August 2005 by the Area Corporate Services Manager and list of projects drawn up by the Area Roads & Amenity Services Manager, submitted)
Word for word from the decision Argyll and Bute published for this meeting.
Source: www.argyll-bute.gov.uk