Resolved
Decision 1. To note the contents of the report and request that this be followed up by Internal Audit; 2. To note that the Action Plan accompanying the report issued by Audit Scotland in August 2005 entitled “Business Continuity Planning Review” contained 3 recommendations and that progress was continuing; 3. To note that the Action Plan accompanying the report issued by Audit Scotland in November 2005 entitled “Financial Strategy” detailed 8 recommendations, 5 of which had implementation dates of between January 2006 and March 2007 with the further 3 recommendations to be in place for the 2007 – 2008 budget cycle; and 4. To note that the Action Plan accompanying the report issued by Audit Scotland at the end of November 2005 entitled “Following the Public Pound” listed 18 recommendations with 2 considered high and 16 of medium priority. (Reference: Report by Internal Audit Manager dated 1 December 2005, submitted)
Word for word from the decision Argyll and Bute published for this meeting.
Source: www.argyll-bute.gov.uk