Strategic Policy Committee (Education) noted this item on Thursday 13 April 2006. Below is the council's own wording, with the papers it was decided on.
Decision To note the contents of the report. (Ref: Report by Director of Community Services dated 30 March 2006, submitted). The Committee resolved in terms of Section 50(A)4 of the Local Government (Scotland) Act 1973 to exclude the public for the following item of business on the grounds that it was likely to involve the disclosure of exempt information as defined in paragraph 9 of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. E1
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
This paper reports on the construction progress at each of the four ‘live’ construction sites as well as an update on the progress towards Financial Close in relation to Hermitage Academy
Recommendation
2.1It is recommended that the Strategic Policy Committee notes the contents of this paper.
3.0DETAIL
The grid below displays the key dates (start construction, target decant and target completion) at each of the four ‘live’ sites. The grid also indicates the construction status at each site as of 3 April 2006. In every case that the Council only has a contract with ABC School - they are our single point of responsibility and single point of accountability. We have no direct contract with either Barr or Mansell, who are sub contractors.
Site Construction Construction Decant Contract Sub Start Status Target Completed Contractors Date Target Date Rothesay Sep 2005 Behind Dec Sep 2007 Barr Joint Schedule 2006 Campus¹
Oban Sep 2005 Behind May Apr 2007 Barr Primary Schedule 2006 Campus² (Phase 1)* Dec 2006 (Phase 2) Lochgilphead Oct 2005 On schedule Oct Oct 2007 Mansell Joint 2007 Campus³ Dunoon Sep 2005 On Schedule Jun Dec 2007 Mansell Grammar 2007 School
¹Rothesay Joint Campus comprises Rothesay Academy and Rothesay Primary. ²Oban Primary Campus comprises Rockfield Primary School, St Columba’s RC Primary School and Drummore Learning Centre. * This date will now not be achieved. ³Lochgilphead Joint Campus comprises Lochgilphead High School, Lochgilphead Primary School and Whitegates Learning Centre.
F:\moderngov\data\published\Intranet\C00000190\M00002534\AI00028573\NPDOProgressReport0304060.doc 1 A request for the reasons for the delay at both of the Barr sites (Rothesay and Oban) has been made together with the requirement for ABC Schools Ltd to produce a revised detailed contract construction timetable (to be reported to a future meeting). Although the decant for Drummore Learning Centre will now not go ahead as targeted on 5 May, at this stage, it is not envisaged that the phase 2 decant at Oban, nor any of the other final decant dates, have been compromised. At present the estimates of how long the delays will be range, from the most optimistic forecast of three weeks late, to, the most pessimistic being ten weeks late. However, this cannot be clarified with any degree of certainty until the Council receives and scrutinises the revised timetable.
It is disappointing that this the first school scheduled for transfer will now be late. However, Members will wish to note that the entire risks of any contract time or price over-run lies entirely with the Contractor, ABC Schools, and not the Council. Under this PPP (Public Private Partnership) contract the Council will only start paying for this school as and when it occupies this school. Until that happens all of the finance for this construction is being funded entirely by the private sector.
Hermitage Procurement
ABC Schools appointed hbg as their preferred bidder for the Hermitage construction in December 2005. Since then hbg have been carrying out their due diligence procedures in relation to the Project Agreement and the commercial terms of this contract. Considerable progress has been made with this procurement and a number of potential difficulties have been resolved and overcome. In addition, most of the items in relation to conditional planning consent have now been resolved and the few that remain will be resolved this week. The original target date for signing of Financial Close was 7 April, however, in order to allow for the resolution of any last minute issues ahead of the Easter public holidays this date has now been revised and is scheduled to take place after the public holidays on 18 April.
5. CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Policy Committee (Education) at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.