Resolved
Decision Noted the content of the report. (Reference: Report by Executive Director – Customer Services dated April 2012, submitted)
Executive noted this item on Thursday 19 April 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the content of the report. (Reference: Report by Executive Director – Customer Services dated April 2012, submitted)
1.1This report summarises progress in relation to the Council’s NPDO project to end of March 2012 and, in particular, provides an update on the current financial position of the Project.
2.1The Executive is asked to note the contents of this report.
3. DETAIL
3.1All five School sites within the NPDO project have now been handed over, including all external works and phases, and are operational.
3.2The Special Projects Team (SPT) continues to attend the regular Board meetings of ABC Schools Ltd and meet regularly with School representatives and representatives from the Council’s partners, ABC Schools Ltd and Mitie PFI, to monitor progress. The SPT continues to utilise the system of liaison meetings and inspections along with assistance from Facility Services to assist in identifying service provision and building fabric issues within the facilities.
4 BUDGET POSITION
4.1At the Executive meeting in August 2008, the SPT was requested, annually, to provide the Executive with confirmation of the ongoing financial status of the NPDO project based on the assumptions prevalent at the time of reporting.
4.2In April 2011 it was reported that, based on assumptions prevalent at the time, the project was affordable in each contract year. For 2011/12 further efficiencies have been identified within the NPDO project relating to performance and availability deductions and savings in insurance costs. These efficiencies have reduced budgetary impact of the NPDO on the Council as a whole.
4.3As part of the 2012/13 budget setting process the Council agreed to remove the NPDO smoothing fund and apply the sums earmarked therein for other purposes. The Council also agreed to fully fund the NPDO budget for the next three years (2012/13, 2013/14 and 2014/15) prior to
D:\moderngov\data\published\Intranet\C00000376\M00005096\AI00065742\April2012NP DOProgressReport0.doc the removal of the NPDO smoothing fund. It is anticipated that, based on current assumptions, the NPDO will be able to be operate for the next three years within the budget allocation set by the Council in February 2012. The budgetary position of the NPDO over the next three years will continue to be reviewed and reported as part of the Council’s budget monitoring process.
Future Pressures
4.4Notwithstanding the above, there continue to be potential cost pressures on the NPDO which will continue for the life of the project and affect its long term budgetary position. These will include fluctuations in the general Retail Price Index (RPI), utility tariff rates and Non Domestic Rates (NDR) where the Council takes the risk on changes to these. The current forecast assumes that these factors will increase in line with overall Council estimates. Despite the removal of the smoothing fund, the SPT intend to maintain a long term forecast of likely NPDO expenditure so that any adverse impacts resulting from these cost pressures can be anticipated, managed and reported as necessary.
5 EFFICIENCIES IDENTIFIED
5.1The SPT are continuing to monitor ongoing availability and performance deductions. Since April 2011, ABC Schools have required to make payment to the Council of approximately £216,000 by way of deductions. The SPT are currently withholding a further sum of about £115,000 by way of disputed deductions and are in discussion with ABC Schools to resolve that matter. The SPT continue to dispute unitary charge invoices, as appropriate, following the contract provision, to enable discussions to negotiate settlement of outstanding deductions due to the Authority.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NPDO SCHOOLS PROJECT PROGRESS REPORTAgenda | 73 KB | DownloadRead as text |
Follow Executive at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2012 | Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... | Noted | Open |
| 19 Apr 2012 | Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.