ELECTRICITY CONSULTATION: ERECTION OF WINDFARM CONSISTING OF 20 TURBINES - CARRAIG GHEAL, INVERINAN, TAYNUILT (05/00016/ELSE36)

Agreed Planning 4 papers

Planning, Protective Services and Licensing Committee agreed this item on Thursday 20 April 2006. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision It was agreed to approve the recommendation of the Oban Lorn & the Isles Area Committee, and to recommend that conditions be remitted to the Director of Development Services in consultation with the Chairman, Vice-Chairman and Local Member. Councillor Al Reay wished his dissent to be recorded. (Ref: Report by the Head of Planning and report dated 5 th April 2006 by the Assistant Area Manager, Roads & Amenity Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

DEVELOPMENT SERVICES Local Member - Cllr Macaskill PLANNING APPLICATION REPORT Date of Validity - 31.12.04 OBAN, LORN AND THE ISLES Committee Date - 08.03.2006

Reference Number: 05/00016/ELSE36 Applicants Name: Green Power Application Type: Electricity Consultation Application Description: Erection of Windfarm Consisting of 20 Turbines Location: Carraig Gheal, Inverinan, Taynuilt

(A ) THE APPLICATION

Development Requiring Express Planning Permission.

• The erection of 20 (originally 24) turbines with tubular towers and a three blade rotor (84m diameter) 9 x 65m at hub, 110m to blade tip, 11 x 80m at hub, 125m to blade tip. • Anemometer mast (for monitoring) lattice, up to 85m tall. • Sub Station at Control Room 34m x 10m • Access Road • Access Track • Temporary construction compound (generic layout) 70m x 50m in temporary security fence containing site accommodation, generator, fuel storage, 3 x secure storage and parking area. • Connections to local electricity grid by underground cables to the existing national grid Taynuilt/Inverinan 132kv overhead system to the east of the site.

There are two possible routes for vehicular delivery of large turbine components under escort. One is from the east from A85 at Taynuilt along the B845 (Glen Nant Road) to a point 1km north of Kilchrenan. One is from the west from the A85, 5km west of Taynuilt along forest roads to Beinn Ghlas and then south to the site.

(B ) DETERMINATION OF THE APPLICATION

Because the proposal will generate over 50kw the decision on this proposal will be made by the Scottish Executive. Argyll & Bute Council is a consultee and the Executive will carry out other consultations and consider representations.

(C ) RECOMMENDATION

It is recommended that the Council inform the Scottish Executive that it is considered that the proposed wind farm should be refused because of the visual impact on the Loch Awe area and the cumulative impact of this proposal and the existing Beinn Ghlas windfarm.

Further that should the Executive decide to grant permission, that vehicular access for turbine deliveries be restricted to the westerly routes to reduce the impact on Glen Nant.

(D ) THE APPLICATION SITE, APPLICATION AND SUPPORTING INFORMATION

The site for the turbines is adjacent to Carraig Gheal at Inverinan. It is an undulating area at a height of about 400m to the west of Kilchrenan and about 3km south of Beinn Ghlas wind farm. This is an area of craggy uplands with commercial forest to the south and to the north east and open woodland to the west and east. F:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000199\M00002441\AI00028623\00016WRIM20.DOC 1 Vehicular access for turbines is by two possible routes. The eastern route is from the A85 at Taynuilt (and would involve improvements to that junction) and along the B845 Glen Nant Road where there would be upgrading of sight lines on some bends. The Westerly route is from Fearnoch, west of Taynuilt following the access route to Beinn Ghlas wind farm and then continuing south to the applicants site.

The proposed development would be visible from a number of viewpoints and these are covered in the Environmental Assessment.

Originally the application was for 24 turbines but following concerns from SNH and RSPB regarding the affect on Golden Eagles the layout was changed and 4 turbines were deleted/repositioned and others changed

SUPPORTING INFORMATION

The application is accompanied by an Environmental Statement (ES) and an amended Environmental Statement.

VISUAL IMPACT

The ES contains views for 21 points. I have assessed these later in the report.

ORNITHOLOGY

The ES concludes that the key species for which there was potential for significant effects were:-

Merlin, Red Throated Diver, Golden Eagles and Golden Plover. The conclusions are that there are no significant impact on these birds.

(E) ASSESSMENT AND MATERIAL DETERMINIGN CONSIDERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
$$MinutesMinutes 54 KB Download
PDF
00016 WR: IM (2)Report 111 KB DownloadRead as text
PDF
Carraig GhealReport 67 KB Download
PDF
ELECTRICITY CONSULTATION: ERECTION OF WINDFARM CONSISTING OF 20 TURBINES: CARRAIG GHEAL, INVERINAN, TAYNUILT (05/00016/ELSE36)Report 75 KB Download

At this meeting

Whole meeting
3MINUTESOn the agenda
4ELECTRICITY CONSULTATION: ERECTION OF WINDFARM CONSISTING OF 20 TURBINES - CARRAIG GHEAL, INVERINAN, TAYNUILT (05/00016/ELSE36)This decision

Who was there

9 of 13 attended
GM
Councillor Gordon McKinvenChair, present
RK
Councillor Ronald KinlochMember, apologies
SM
Councillor Sidney MacDougallVice-Chair, present
RC
Councillor Robin CurrieMember, apologies
JF
Councillor Jim FindlayMember, apologies
JG
Jane GilliesSecretary, present
AG
Angus GilmourOfficer, present
BM
Councillor Bruce MarshallMember, present
JM
Councillor John McAlpineMember, present
DM
Councillor Donald McIntoshMember, apologies
AR
Councillor Al ReayMember, present
CR
Charles ReppkeOfficer, present

All 13 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ELECTRICITY CONSULTATION: ERECTION OF WINDFARM CONSISTING OF 20 TURBINES - CARRAIG GHEAL, INVERINAN, TAYNUILT (05/00016/ELSE36)This decision
  2. The scottish government on behalf of energiekontor uk ltd: electricity act section 36 consultation relevant to breackerie wind farm: land approximately 8km south west of campbeltown (ref: 23/02230/s36)Agreed
  3. The scottish government on behalf of blarghour wind farm limited: electricity act section 36c and electricity generating stations (applications for variation of consent) (scotland) regulations consultation from the energy consents unit forAgreed
  4. The scottish government on behalf of scottish power renewables (uk) limited: electricity act section 36 consultation for earraghail renewable energy development, comprising thirteen onshore wind turbines around 78mw, solar photovoltaic arraAgreed
  5. The scottish government on behalf of energiekontor uk ltd: electricity act section 36 consultation relevant to rowan wind farm: land approximately 4.5km north west of tarbert, argyll & bute (ref: 22/00385/s36)Agreed
  6. The scottish government on behalf of drax cruachan expansion limited: electricity act section 36 consultation relevant to construction and operation of new underground power station and associated infrastructure adjacent to cruachan 1 to prAgreed

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies