Decision It was agreed to approve the recommendation of the Oban Lorn & the Isles Area Committee, and to recommend that conditions be remitted to the Director of Development Services in consultation with the Chairman, Vice-Chairman and Local Member. Councillor Al Reay wished his dissent to be recorded. (Ref: Report by the Head of Planning and report dated 5 th April 2006 by the Assistant Area Manager, Roads & Amenity Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
DEVELOPMENT SERVICES Local Member - Cllr Macaskill PLANNING APPLICATION REPORT Date of Validity - 31.12.04 OBAN, LORN AND THE ISLES Committee Date - 08.03.2006
Reference Number: 05/00016/ELSE36 Applicants Name: Green Power Application Type: Electricity Consultation Application Description: Erection of Windfarm Consisting of 20 Turbines Location: Carraig Gheal, Inverinan, Taynuilt
(A ) THE APPLICATION
Development Requiring Express Planning Permission.
• The erection of 20 (originally 24) turbines with tubular towers and a three blade rotor (84m diameter) 9 x 65m at hub, 110m to blade tip, 11 x 80m at hub, 125m to blade tip. • Anemometer mast (for monitoring) lattice, up to 85m tall. • Sub Station at Control Room 34m x 10m • Access Road • Access Track • Temporary construction compound (generic layout) 70m x 50m in temporary security fence containing site accommodation, generator, fuel storage, 3 x secure storage and parking area. • Connections to local electricity grid by underground cables to the existing national grid Taynuilt/Inverinan 132kv overhead system to the east of the site.
There are two possible routes for vehicular delivery of large turbine components under escort. One is from the east from A85 at Taynuilt along the B845 (Glen Nant Road) to a point 1km north of Kilchrenan. One is from the west from the A85, 5km west of Taynuilt along forest roads to Beinn Ghlas and then south to the site.
(B ) DETERMINATION OF THE APPLICATION
Because the proposal will generate over 50kw the decision on this proposal will be made by the Scottish Executive. Argyll & Bute Council is a consultee and the Executive will carry out other consultations and consider representations.
(C ) RECOMMENDATION
It is recommended that the Council inform the Scottish Executive that it is considered that the proposed wind farm should be refused because of the visual impact on the Loch Awe area and the cumulative impact of this proposal and the existing Beinn Ghlas windfarm.
Further that should the Executive decide to grant permission, that vehicular access for turbine deliveries be restricted to the westerly routes to reduce the impact on Glen Nant.
(D ) THE APPLICATION SITE, APPLICATION AND SUPPORTING INFORMATION
The site for the turbines is adjacent to Carraig Gheal at Inverinan. It is an undulating area at a height of about 400m to the west of Kilchrenan and about 3km south of Beinn Ghlas wind farm. This is an area of craggy uplands with commercial forest to the south and to the north east and open woodland to the west and east. F:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000199\M00002441\AI00028623\00016WRIM20.DOC 1 Vehicular access for turbines is by two possible routes. The eastern route is from the A85 at Taynuilt (and would involve improvements to that junction) and along the B845 Glen Nant Road where there would be upgrading of sight lines on some bends. The Westerly route is from Fearnoch, west of Taynuilt following the access route to Beinn Ghlas wind farm and then continuing south to the applicants site.
The proposed development would be visible from a number of viewpoints and these are covered in the Environmental Assessment.
Originally the application was for 24 turbines but following concerns from SNH and RSPB regarding the affect on Golden Eagles the layout was changed and 4 turbines were deleted/repositioned and others changed
SUPPORTING INFORMATION
The application is accompanied by an Environmental Statement (ES) and an amended Environmental Statement.
VISUAL IMPACT
The ES contains views for 21 points. I have assessed these later in the report.
ORNITHOLOGY
The ES concludes that the key species for which there was potential for significant effects were:-
Merlin, Red Throated Diver, Golden Eagles and Golden Plover. The conclusions are that there are no significant impact on these birds.
(E) ASSESSMENT AND MATERIAL DETERMINIGN CONSIDERATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.