Resolved
Decision Agreed to approve the proposed allocations of additional budget as detailed in report. (Reference: Report by Area Roads Amenity Services Manager dated 6 June 2006)
Helensburgh & Lomond Area Committee agreed this item on Tuesday 6 June 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Agreed to approve the proposed allocations of additional budget as detailed in report. (Reference: Report by Area Roads Amenity Services Manager dated 6 June 2006)
This report provides further information on the roads revenue budget to fund the Work Programme in the Helensburgh / Lomond area in 2006/7.
That the Area Committee approves the proposed allocations of additional budget as detailed in Appendix 1A.
3.1The previous report advised of the indicative figures before finalisation of the budget process. A further £59,342 has been allocated bringing the Revenue Budget to a revised total of £1,101,770.
4. Routine Revenue £1,101,770
. 4.1 It is proposed to allocate this as detailed in Appendix 1A subject to the approval of the committee.
4.2It is necessary to increase Activity 401 Surface Dressing by £8,000 This increase was discussed with the Area Chair and was necessitated by a significant increase in bitumen costs and stone chips and the work has now been completed.
4.3It is proposed to increase Activity 501 Carriageway Patching by £27,342. This will assist in completing the resurfacing of the B833 Junction at the Clachan that has been carried over from last year.
4.4It is proposed to increase Activity 1001 Footway resurfacing by £20,000. This will permit the resurfacing of the footway at Sinclair Street ( Victoria Halls) to be completed which has been outstanding for some years awaiting the works the gates.
4.5It is proposed to increase Activity 1101 Kerbing that will allow further dropped kerbs to be installed 5. Implications
Policy: None Financial: All costs will be contained within the proposed budgets. Personnel: None Equal Opportunity: None Legal: None
For further information contact Alan Kerr (01436 658877) Appendix 1 – Routine Revenue Works
Activity 2006/7 Additional Revised 501 C/W Patching 159,188 27,324 186,512 502 C/W Potholing 100,000 401 Surface Dressing 80,000 8,000 88,000 Carriageways 339,188
1001 F/W Resurface / patch 80,000 20,000 100,000 1101 Kerbing 2,000 4,000 6,000 Footways 82,000
3201 Emergencies 5,000 3501 Sweeping 1,000 Miscellaneous 6,000
1402 Drainage Ditches 30,000 1501 Verges 45,000 1502 Verge Drainage 1,000 1503 Weed Control 10,000 1601 Trees 8,000 1801 Gullies 70,000 Routine 164,000
1301 Earthworks 15,000 1401 Culverts 140,000 2001 Fences 1,000 Structural 156,000
2601 Gritting 238,240 Winter 238,240
2101 Ped Guardrails 1,000 2401 Veh. Safety Fence 10,000 1702 Road Mark/ Studs 20,000 2202 Traffic Signal Maintenance 3,000 2212 Ped. Crossing Maintenance 1,000 2302 Traffic Signs Maintenance 17,000 2411 Street Name Plates 5,000 Traffic 57,000 Total Roads Revenue 1,042,428 59,324 1,101,752
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Road Works Programme 2006-2007Report | 89 KB | DownloadRead as text |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.