Report on Annual Development Control Performance Council Wide and Decentralised Area Team Performance to June 2006

Agreed Committee 1 paper

Oban Lorn & The Isles Area Committee agreed this item on Thursday 6 July 2006. Below is the council's own wording, with the papers it was decided on.

Item5k

Resolved

It was agreed to: (a) note and endorse the report, with particular regard to workload review, the introduction of the Uniform public access module and document management; (b) agree a Council wide target of 69% for processing all applications for the period from April 2006 to March 2007; (c) continue to adopt the Scottish Executive target of deciding 90% of householder applications over the same period; and (d) agree the decentralised target of 66% for the Oban , Lorn & the Isles area. (Ref: Report by the Head of Planning, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Summary

1.1This paper outlines my services Development Control performance with respect to planning applications, reports progress on the key Service Plan targets and provides the results on the exit questionnaires.

1.2Unfortunately, my service failed to reach the target of processing 72% of planning applications within two months. For the third year in a row performance has stayed at 64%.

1.3With respect to householder applications, 89% were processed within two months. Whilst this represents the same level of performance as last year it is 1% below the target of 90%.

1.4Whilst it is recommended that the targets for the decentralised areas remain largely the same as last year, with the exception of Bute & Cowal being lowered, the targets are considered to be reasonably achievable. It is considered that there is no benefit of setting unrealistically high targets that cannot be met.

1.5Whilst application numbers have remained reasonably stable, there is the perception that there has been an increase in “major” or “environmental impact assessment” type applications, although this cannot be readily confirmed. Similarly, it is perceived that there has been increases in “preliminary enquiry” letters which again cannot be readily confirmed. In respect of the above, it is intended that over the next year measures to monitor “major” and “environmental Impact Assessment” developments and to record preliminary enquiries will be introduced. It is also intended to record and monitor not only applications received by area team but also application type.

Recommendation

2.1It is recommended that Members:

a) Note and endorse the contents of the report, with particular regard to workload review, the introduction of the Uniform public access module and document management. b) Agree a Council wide target of 69% for processing all applications for the period April 2006 to March 2007. c) Continue to adopt the Scottish Executive target of deciding 90% of householder applications over the same period. d) Agree the decentralised targets specified below:

• Bute and Cowal 65% Drop of 13% • Helensburgh and Lomond 80% No change • Oban, Lorn and the Isles 66% No change • Mid Argyll, Kintyre and Islay 66% No change

3.0COUNCIL WIDE DEVELOPMENT CONTROL PERFORMANCE APRIL 2005 – MARCH 2006

TABLE 1: TARGETS AND ACHIEVEMENTS SINCE 1996

TABLE 1: TARGETS AND ACHIEVEMENTS SINCE RE-ORGANISATION % OF ALL APPLICATIONS DEALT WITH WITHIN TWO MONTHS YEAR APPLICATIONS APPLICATIONS TARGET ACHIEVED RECEIVED DETERMINED 1996/97 1402 1162 57% 46% 1997/98 1482 1355 57% 63% 1998/99 1519 1318 67% 67% 1999/2000 1507 1340 69% 65.3% 2000/2001 1529 1252 68% 66% 2001/2002 1614 1420 71% 66% 2002/2003 1692 1490 71% 69% 2003/2004 1813 1512 72% 64% 2004/2005 2112 1718 72% 64% 2005/2006 2030 1744 72% 64% 3.1 As can be seem from Table 1, Development Control performance remains at the same level of 64% for the third year in a row.

3.2Whilst the number of applications received has “levelled out” over the last year, my service has processed an increased number. This increase in the number of applications processed is encouraging as it indicates a reduction in “backlog.”

3.3Whilst the evidence cannot be readily extracted, there is the perception that whilst numbers of applications have not increased, there has been a significant increase in “major” and “environmental impact assessment” applications. The potential increase in these types of application has the implication of reducing an area teams ability to increase performance due to the amount of staff time required to process large, complex applications. In order to assess the impact and consider options for dealing with these applications it is intended to start to record application types.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report on Annual Development Control Performance Council Wide and Decentralised Area Team Performance to June 2006Report 92 KB DownloadRead as text

At this meeting

Whole meeting
3aMinutes of Oban Lorn & the Isles Area Committee meeting held on 7th June 2006On the agenda 3bOban, Lorn & the Isles Area Corporate Priorities 2006-2008Agreed 4aApplications for financial assistance under the Leisure Development Grant SchemeDecided 5aList of Building Standards delegated decisions issued by the Director of Development Services since the last meetingOn the agenda 5bList of Town and County Planning delegated decisions issued by the Director of Development Services since the last meetingOn the agenda 5c05/00907/DET; Mrs P M Angier; Detailed Application - Erection of 2 Dwelling Houses - Barochreal, KilninverOn the agenda 5d06/00373/OUT; John S. MacPhail; Outline Application - Site for the erection of dwellinghouse - Little Erray, Raeric Road, Tobermory.On the agenda 5e06/00497/DET; Mr and Mrs P. Beattie; Detailed Application - Erection of a Dwelling - West of Inshaig Park House, EllenabeichOn the agenda 5f06/00630/OUT; Mr & Mrs A. Colthart; Outline Application - Erection of a Dwellinghouse - Vacant Plot, Tynribbie, AppinOn the agenda 5g06/00746/OUT; Colin D. Campbell; Outline Application - Erection of a Dwellinghouse - Tighgrianach, North ConnelOn the agenda 5h06/01091/OUT; Paul Gallagher; Outline Application - Site for the erection of one dwellinghouse - Raeric House, Raeric Road, Tobermory.On the agenda 5iReporter's Decision in regard to planning application ref. 05/00093/ENFOTHOn the agenda 5jReporter's Decision in regard to planning application ref. 05/00450/OUTOn the agenda
5kReport on Annual Development Control Performance Council Wide and Decentralised Area Team Performance to June 2006This decision
5lReport on Building Standards Performance Monitoring and Service Plan progress Council Wide and Decentralised Area Tems for 2005/2006On the agenda 6PUBLIC QUESTION TIMEOn the agenda 23The Committee resolved in terms of Section 50(A)(4) of the LocalOn the agenda

Who was there

12 of 22 attended
AM
Councillor Alistair MacDougallChair, present
AM
Councillor Allan MacaskillMember, apologies
IG
Councillor Ian GilliesVice-Chair, present
RB
Councillor Robin BanksMember, present
SM
Councillor Sidney MacDougallMember, present
IM
Iona MacPhailOfficer, present
HB
Hugh BlakeOfficer, present
NB
Neil BrownOfficer, absent
CE
Carol EvansOfficer, absent
JG
Jane GilliesSecretary, present
DK
Donald KellyOfficer, absent
KM
Kenneth MacdonaldOfficer, present

All 22 on the meeting page

On this subject at Argyll and Bute

Search all
  1. Report on Annual Development Control Performance Council Wide and Decentralised Area Team Performance to June 2006This decision
  2. Registration of an economic development subsidy scheme to facilitate compliance with post-eu subsidy control legislationNoted
  3. Caravan sites and control of development act 1960 new licensing system for mobile home sites with permanent residentsAgreed
  4. Caravan sites and control of development act 1960 - new licensing system for mobile home sites with permanent residentsAgreed
  5. Fyne futures ltd: erection of 3 wind turbines (100 metres high to blade tip), control building, new and improved access tracks and ancillary development: land south of auchadaduie, barr glen, glenbarr, kintyre (ref: 11/02525/pp)Agreed
  6. A'chruach wind farm limited: windfarm comprising 21 turbines (126.5 metres high to blade tip), erection of 2 meteorological met masts, sub station, control building, construction compounds, access works and ancillary development (amended prAgreed

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open