Decision The Area Committee: Approved the proposals in Appendix 1 and 2. Requested that a paper be brought to the November Area Committee on unadopted roads in Bute and Cowal Councillor Macintyre wished his dissent regarding money being spent on repairing Bruchag Road to be recorded in the minutes. (Reference: Report by the Area Roads & Amenity Services Manager – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The purpose of this paper is to seek approval of the proposed roads works programme funded from the Council’s Capital Programme.. . 2. RECOMMENDATIONS
That Members approve the proposals
3. BACKGROUND ROADS The Council’s capital allocation for roads reconstruction 2006-7 is £2.543m and this is shared between areas with Bute and Cowal receiving 20% - £508,600. Proposals amounting to that figure have been circulated to Members for information and comment. As a result of the Council’s Capital Plan being reconsidered in June a further £549,000 has been provided- again this area share amounts to £109,800. The increased works programme proposals are shown in Appendix 1 with location of the proposals shown in Appendix 2.
FOOTWAYS Under the Cycling Walking and Safer Streets programme there is £40,000 available and the intended schemes are shown in Appendix 3 Members attention is drawn to a request has been made for assistance in investigation and design costs for the proposed remote footway to the new schools campus and Members approval is sought to contribute £10K to this project subject to the full scheme funding being developed and this contribution realised as part of the overall cost.
5. BACKGROUND PAPERS Appendix 1 – Proposed capital Works Programme 2006-07-06 Appendix 2 – Proposed works programme – location plan.
For further information, please contact Alan Lothian, Area Manager, Roads & Amenity Services 01369 708600. Appendix 1
BUTE & COWAL CAPITAL WORKS. PROGRAMME 2006- 2007. Budget Total £618,400 S/Dressing Bute & Cowal £67,000 Committed Surfacing in Cowal £448,654 Surfacing in Bute £102,746 RESURFACING WORKS 2006/7 Ward Route Location Estimated Comments No No Cost Cowal 25 A815 Osbourne Hotel - north to road Xing £21,500 Completed 25 A815 Burnakamin Brae to Chirnside £21,500 Completed Council owned unmade 25 Unadopted South Campbell Road, Innellan £48,200 track 26 Various Dunoon Traffic Management Scheme £10,000 25 A815 Ardchyline Sections 1 & 3 £71,800 Wearing course deterioration & road edge failure 21 B8000 14 locations £104,614 Structural failure due to heavy axle loadings 21 A815 Coire Ealt £98,040 Wearing course deterioration & Structural failure 21 B839 Hells Glen Moses Well £22,500 Structural failure due to heavy axle loadings 21 A815 Strachur hall to A886 £17,000 Wearing course deterioration 21 C6 Carrick Castle Rd 3 locations £33,500 Wearing course deterioration Sub Total £448,654 Bute 20 UC 40 John Street £8,000 Wearing course deterioration 18 C1 Bruchag Road £32,500 Structural failure due to heavy axle loadings 20 B881 KILCHATTAN - POLICE HOUSE HEADING SOUTH £24,540 Wearing course deterioration 20 B881 KILCHATTAN - CORNER, 6m WEST 30/40 HEADING WEST £9,706 Wearing course deterioration 19 B881 KILCHATTAN - St BLANES HOTEL, MEADOW - 9 St BLANES VILLA £28,000 Wearing course deterioration Sub Total £102,746 Appendix 2 Bute & Cowal Capital Resurfacing Programme 2006-2007
B839 Hells Glen ` A815 Ardchyline
A815 Strachur
C6 Carrick Castle Road
A815 Coire Ealt
B8000
A815 Innellan
South Campbell Rd Unadopted
UC40 John St
C1 Bruchag Rd
B881 Kilchattan Appendix 3
Cycling Walking and Safer Streets Programme – Funding available £40,000
Cowal Location Estimate Description A815 Sandbank Shops – McKinlay’s Quay 16,000 Reconstruction of footway A885 Finbracken to MacDonald Avenue 8,000 Reconstruction of footway
Bute Design and investigation costs for New Schools 10,000 Campus pedestrian and cycle route UC 33 Glebe Terrace, Rothesay 6,000 Reconstruction of footway some with heavy duty construction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.