DEVELOPMENT SERVICES Local Member - Councillor- J.R. Walsh PLANNING APPLICATION REPORT Date of Validity - 6th December 2005 Bute and Cowal Area Committee Date - 1st August 2006
24th July 2006
Reference Number: 05/02439/DET Applicants Name: Scottish Water Solutions Application Type: Detailed Application Description: Stabilisation of rockface; Erection of Waste Water Treatment Works, ancillary development and alterations to existing access: Location: Bullwood Quarry, Bullwood Road, Dunoon
Supplementary Report
(A ) BACKGROUND
This application was considered by the Area Committee at its meeting on 4 July 2006. Members agreed that a PAN 41 Hearing with no recommendations be held prior to the determination of this application and that Scottish Water be required to produce a range of further information prior to the hearing. This decision was conveyed to the applicants by an Article 13 direction. The response from the applicant’s agent (attached as an appendix to this report) has intimated that most of the information can be provided with the exception of certain photomontages. It is also understood that the agent will be able to provide a physical scale model of the site at the hearing.
Although this information will not fulfil all the requirements set by the Committee, it is considered that it should represent a reasonable basis of information on which to convene a hearing and fully consider the merits of the application.
(B ) RECOMMENDATION It is therefore recommended that Members accept this variation in the requested level of information and agree to arrange a discretionary hearing at a suitable date following receipt of the additional information
Angus J Gilmour Head of Planning Services
Case Officer: B. Close 01369-708604 Area Team Leader D. Eaglesham 01369-708608
[name removed] Planning Manager Argyll and Bute Council SCOTTISH WATER SOLUTIONS Milton House Milton Avenue Leven House Dunoon Balmore Road Glasgow PA23 7DU G22 6NP
PLANNING APPLICATION 05/02439/DET DUNOON WASTE WATER TREATMENT WORKS
Further to your letter received 13th July 2006 and our telephone conversation this week, we confirm that we would be pleased to supply further information for the Committee in relation to the above planning application. However, we would ask that consideration is given to the following.
While we are able to produce photomontages for the site during daylight hours from the road and, providing we can obtain the owner’s permission, the adjoining property, we request that the requirement for the following photomontages is withdrawn:
• Photomontages at night. We would suggest that photomontages at night would not serve any meaningful purpose. The site will not be lit up at night except for task lighting and this will only be within operational hours (except in the event of an emergency). Furthermore, at this time of year it would be difficult to obtain the necessary photographs for these.
• Photomontages from the sea. The main route that the public would view this from is the ferry. Neither of the ferries passes close to the site so the montages would not show anything productive. The other option would be to charter a boat however we do not anticipate that the photograph would be of a suitable quality.
With the exception of the above noted items, we undertake to provide the information by 4th September 2006 and would welcome the PAN 41 Hearing as soon as possible after this date. We would be grateful if you would advise of the date as soon as possible.
Finally, we agree that the date for determination of the application can be extended until 31st August 2006.
We look forward to receiving your response in relation to the above. Should you require further information or clarification please do not hesitate to contact us.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies