Decision The Committee agreed – 1. To recommend to the Strategic Policy Committee that should funding become available in 2006/2007, Islay and Jura Community Enterprise Limited be favourably considered for £15,000, and, 2. To receive a report to the next Area Committee on the meeting being held between the Leader of the Council and the Manager of Islay and Jura Community Enterprise Limited on Thursday 3 August 2006. 3. To receive a report at the October meeting from the Head of Community Regeneration on the outcome of this discussions with Islay and Jura Community Enterprise Limited. (Reference – Report by Head of Community Regeneration, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
This paper addresses questions raised at the Mid Argyll, Kintyre and Islay Area Committee of 5th July 2006 during a presentation by Islay and Jura Community Enterprise Limited.
Recommendations
It is recommended that the committee note the contents of this report.
3. DETAILS
The presentation by Islay and Jura Community Enterprise Limited to Mid Argyll, Kintyre and Islay Area Committee on 5th July 2006 raised some questions that members wished addressed. The questions and explanations are shown below.
a. Grant assistance to IJCE Ltd was agreed by MAKI Area Committee on 7th November 2001 and ratified by the full Council on 13th December 2001. The decision of the committee was; 1. Members recommended that the Council in addition to existing core funding, allocates an additional £15,000 per annum for the financial years 2002/2003, 2003/2004 and 2004/2005 to fund the ongoing operation of the Mactaggart Leisure Centre. 2. Members recommended that both the Core Funding and the additional contribution be subject to an annual inflationary increase in line with the standard rate applicable to Council budgets.
On 13th February 2003, 12th February 2004, 10th February 2005 and 9th February 2006 at the Revenue Budget meetings of the Council, decisions were taken regarding savings and budget constraints that affected the budget head providing this funding resulting in the standard rate applicable to Council budgets being frozen or reduced.
b. IJCE Ltd Chair and General Manager met with officials of Community Regeneration on 24th February 2006 to discuss their funding and forecast financial position. As a consequence of the meeting IJCE Ltd were asked to provide details of a Trust which was supplying funding to the company and a copy of their 2006-7 business plan as well as a copy of their audited accounts for 2005-6. These documents, apart from details of the Trust were supplied to officials on 6th July 2006. The documents are currently being examined and other information is awaited before a full appraisal of the company’s situation can be carried out.
c. IJCE Ltd state that they have never received notification of their grant amount at the beginning of the financial year. Any delay in notification would be the result of any delay in the Council budgets being set and cascaded down to budget holders. Normally this would be resolved within the first quarter of the financial year and I have no knowledge of a difficulty in supplying this information on request. For 2006-7 IJCE were notified of their grant amount by e-mail and verbally on 21st April 2006. Over the past few years the Council have accommodated the company with early payments to assist the company’s cash flow.
It should be noted that the company’s financial year is 1st February to 31st January which is not concurrent with the Council’s financial year and revenue budget setting, making any notification of grant to the company prior to the commencement of their financial year difficult.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies