Land Use Consultants Report on Dunoon and the National Park Gateway

Agreed Committee 1 paper

Bute and Cowal Area Committee agreed this item on Tuesday 5 September 2006. Below is the council's own wording, with the papers it was decided on.

Item4h

Resolved

Decision The Committee:- Endorsed the conclusions and recommendations in the Dunoon and the National Park Gateway Strategic Development Framework and Action Plan. Agreed to refer the Action Plan to the Strategic Policy Committee for formal adoption by Argyll and Bute Council. Agreed to request the Strategic Policy Committee to consider the resource implications of implementing the Action Plan and to include appropriate amounts in future budgets which will reflect the priorities identified in the Corporate Plan and related Area Strategy. (Reference: Report by the Development Projects Manager – submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Bute and Cowal Area Committee

Summary

1.1This Strategic Development Framework and Action Plan was jointly commissioned with Argyll and the Islands Enterprise and Loch Lomond and the Trossachs National Park. The report by consultants Land Use Consultants (LUC) is now complete. It sets out to identify the actions that will be required to ensure that the greater Dunoon, eastern Cowal and the Argyll Forest area maxims opportunities, taking the community carefully but confidently into a new era of sustainable growth, creativity and prosperity. It particularly addresses the opportunities that are emerging as result of Dunoon’s close proximity and potential gateway status to the National Park. The broad terms of the report are recommended for endorsement by the Area Committee.

Recommendations

2.1That the conclusions and recommendations in the Dunoon and the National Park Gateway: Strategic Development Framework and Action Plan be endorsed by the Area Committee.

2.2That the Action Plan be referred to the Strategic Policy Committee for formal adoption by Argyll and Bute Council.

2.3That the Strategic Policy Committee be requested to consider the resource implications of implementing the Action Plan and to include appropriate amounts in future budgets which will reflect the priorities identified in the Corporate Plan and related Area Strategy.

Background

3.1The draft report has been considered by the Dunoon Action Plan Steering Group and various amendments have now been incorporated into the final report.

3.2The recommendations in LUC report require formal endorsement by the Council. There are then two key issues that require to be considered by the Council and its partners. Firstly the establishment of a delivery mechanism to take forward the action plan and secondly the identification, allocation and prioritisation of the internal resources required to underwrite the process.

3.3The Steering Group has considered the first steps to be taken in the implementation process and recommends the establishment of a Leadership Group. This would involve representatives from the three agencies meeting periodically to review progress on the themed components of the action plan. Each agency would have lead responsibility for appropriate elements of the action Plan. Further consideration would need to given by the Leadership group to ongoing community involvement.

4. CONCLUSION

4.1This strategic framework provides a structure for action that aims to address established problems and seize opportunities that are emerging from the National Park. Full endorsement and commitment by the Council is essential to its success.

5. IMPLICATIONS

Policy: Furtherance of the Council’s Corporate Strategy, Area Strategy and Local Plan. Financial: Existing capital commitments at Queen’s Hall and Dunoon Pier. Consideration to be given to additional contributions to underwrite the delivery mechanism and key projects. Personnel: Significant officer involvement. Equal Opportunity: None

For further information contact: Kevin Williams Telephone 01546 604274

LIST OF BACKGROUND PAPERS: Dunoon and the National Park Gateway: Strategic Development Framework and Action Plan. Land Use Consultants, August 2006

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Land Use Consultants Report on Dunoon and the National Park GatewayReport 54 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
BC
Councillor Brian ChennellChair, present
DC
Councillor Douglas CurrieMember, present
GM
Councillor Gordon McKinvenMember, present
AL
Alan LothianOfficer, present
RM
Councillor Robert MacintyreMember, present
BM
Councillor Bruce MarshallVice-Chair, present
JM
Councillor James McQueenMember, present
JR
Jo RainsOfficer, expected
LS
Councillor Len ScoullarMember, present
IS
Councillor Isobel StrongMember, apologies
DW
Councillor Dick WalshMember, apologies

On this subject at Argyll and Bute

Search all
  1. Land Use Consultants Report on Dunoon and the National Park GatewayThis decision
  2. Consider notice of review request: land south of kilfinan community forest caravan and west of hafton house, tighnabruaich (ref: 20/01429/pp)Agreed
  3. Mr lorne marshall: change of use of land to form timber storage and firewood processing area (part retrospective): na tri gleann, sandbank, dunoon (ref: 24/01882/pp)Agreed
  4. Consider notice of review request: vacant land north west of finnart farmhouse, feuins road, portincaple (ref: 24/0017/lrb)Agreed
  5. Lorne thomson: change of use of land to vehicle parking/storage, including laying of hardcore, erection of boundary wall and formation of access (part retrospective): land west of bt telephone exchange, garelochhead (ref: 24/01249/pp)Agreed
  6. Ms erin murphy: erection of a fence and use of land as the curtilage of a shop unit: land to the rear of 19 east princes street, rothesay, isle of bute (ref: 24/01459/pp)Agreed

More from Argyll and Bute Bute and Cowal Area Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... Noted Open
1 Sep 2026 Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... Noted Open
1 Sep 2026 Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... Agreed Open
1 Sep 2026 Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... Noted Open
1 Sep 2026 Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies