Resolved
Decision The Committee agreed:- 1. To establish a Project Board for the Dunoon Seafront Development to identify future use of the Pier and its buildings as identified in the Corporate Plan comprising 3 Members of the Bute and Cowal Area Committee and 3 Officers of the Council. 2. That the Pier sub-structure scheme is progressed after a business case has been developed and an agreed funding mechanism has been secured following on from the recommendation above and that this progress be reported back to the Strategic Policy Committee; and 3. That a ground investigation contract for the sub-structure be prepared only after decision 2 above has been concluded, as to proceed otherwise would risk the cost being charged to a revenue account if the scheme did not result in the creation of an additional asset. (Reference: Report by Director of Operational Services dated 4 December 2006, submitted).