Resolved
Decision To agree that the Director of Operational Services appoints a consultant to undertake a specialist study into the wave and sediment regime. (Reference: Report by Director of Operational Services dated 14 January 2008, submitted).
Executive agreed this item on Thursday 24 January 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To agree that the Director of Operational Services appoints a consultant to undertake a specialist study into the wave and sediment regime. (Reference: Report by Director of Operational Services dated 14 January 2008, submitted).
The purpose of this report is to seek approval to engage a specialist consultant to assist in a wave and sedimentation study for the Dunoon Pier Sheet Piling project.
The Members are asked to approve that the Director of Operational Services appoints a consultant to undertake a specialist study into the wave and sediment regime.
3.1The Dunoon Pier Sheet Piling project was initiated in 2004 in connection with the scheme to sheet pile around the main part of the pier. In 2007 the Dunoon Waterfront Group was formed to consider the wider waterfront area of the town but also included the future of the pier. The public consultation undertaken at the end of 2007 showed strong support for a new marina type facility in place of the existing pier together with reclamation of land from the sea to offer an opportunity for new waterfront buildings to be constructed.
3.2The preliminary shape and location of the proposed harbour to protect the marina can only be determined following a study into the wave and sediment patterns existing in the area at present. This is best done during the winter. This information would then allow appropriate modelling of the proposals to be undertaken to ensure that the harbour affords suitable wave protection to the marina and to identify the long term siltation regime.
3.3The study requires the appointment of a specialist consultant to undertake this work.
6. IMPLICATIONS
Policy: None Legal: None Personnel: Some officer time will be required to manage the consultant Financial: The study can be funded from the existing allocation within the Capital Programme. The estimated cost is £15,000. Equalities Impact None Assessment:
For further information please contact Arthur McCulloch, Principal Engineer on 01546 604632.
Stewart Turner Head of Roads & Amenity Services 14 January 2008
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DUNOON PIER SHEET PILING PROJECTReport | 47 KB | DownloadRead as text |
Follow Executive at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2012 | Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... | Noted | Open |
| 19 Apr 2012 | Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.