06/02030/MFF: Mainstream Scotland Ltd: Renewal and modification of existing lease - Camas Bruaiche Ruaidhe
AgreedCommittee3 papers
Oban Lorn & The Isles Area Committee agreed this item on Wednesday 7 February 2007. Below is the council's own wording, with the papers it was decided on.
Agreed to approve renewal of the lease subject to (a) conditions 2 and 4 and the appended advice as set out in the supplementary report No.1 dated 29 January 2007 by the Head of Planning; (b) the amendment of condition 1 to read ‘the lease shall run until 1 st August 2009’; (c) the amendment of condition 3 to reflect restriction of operation of acoustic seal deterrent devices between the hours of 2100 to 0800. (Ref: Report by the Head of Planning dated 27 November 2006 and Supplementary Report No.1 dated 29 January 2007, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
DEVELOPMENT SERVICES Local Member - Councillor E. Robertson PLANNING APPLICATION REPORT Date of Validity - 19th September 2006 OBAN, LORN AND THE ISLES Committee Date - 7th February 2007
29th January 2007
Reference Number: 06/02030/MFF Applicants Name: Mainstream Scotland Ltd Application Type: Marine Fish Farm Application Description: Renewal and modification of existing lease Location: CAMAS BRUAICHE RUAIDHE
SUPPLEMENTARY REPORT 1
1. The application for the renewal of the fish farm lease at Camas Bruaiche Ruaidhe was continued at the January meeting of the Area Committee so that a further report could be made on the matters set out below.
2. Expiry of the Current Lease. The current lease expired at the end of August 2006. The application for renewal was lodged in June.
3. Operation of the Acoustic Seal Deterrent Devices.
The earlier report had recommended the restriction of the working of the acoustic deterrents to daylight hours. Your Committee considered this to be too vague.
The applicant has proposed that the current, unrestricted measures be used from mid August, over the winter, until the end of May. This is the time when predation is most intense. In the period May to August (weeks 20 to 34) the devices would be switched off and only used if an otherwise uncontrollable seal problem arises.
This arrangement appears to be a reasonable one; however there is an overlap in April/May and September with popular boating times. I would therefore suggest that a compromise would be to frame a condition which meets the operator’s requirements but extends the period of exceptional use only from mid-April to mid-September. The condition would read:
“During weeks16 to 37 inclusive no acoustic predator control measures shall be used unless there is a sustained seal attack which cannot be controlled by any other means.
Reason: To limit disturbance of recreational users of the immediate surroundings which form part of an established area of moorings.”
4. The Scheme of Visual Mitigation Measures. The Applicants have responded, “In recent months we have removed the automatic feeding system that was present on the site. This has reduced the number of gulls present on the site and has generally simplified the look of the operation. We have also recently removed the orange generator that was on site and this will be replaced by one with a grey neutral colour scheme. In general we have a policy to keep all unused equipment off the site and for our staff to remove all feed bags and associated rubbish on a daily basis to be disposed of by compaction at our shore based facilities.” The condition as previously presented was intended to formalise these improvements, but given that significant steps have been taken, and in the absence of any other pressing concerns, it is recommended that this condition be omitted.
5. It is recommended, as before, that the lease be renewed for a three year period subject to the following conditions:
F:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000245\M00002745\AI00033146\2030SR1RW2901070.DOC 1 CONDITIONS AND REASONS RELATIVE TO APPLICATION 06/02030/MFF
1. The lease shall run for three years from its grant or until 1st March 2010 whichever is earliest.
Reason: The Draft Argyll and Bute Local Plan designates surrounding areas as a potential development area and an area for action and requires the production of a coastal framework plan. These designations and plans are likely to significantly change the planning context of the site and give rise to potential conflicts with other users of the Loch.
2. The farm shall be stocked with trout. .
Reason: The District Salmon Fishery Board advises that the site is close to important salmon rivers and therefore unsuitable for salmon production.
3. During weeks16 to 37 inclusive no acoustic predator control measures shall be used unless there is a sustained seal attack which cannot be controlled by any other means.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.